GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1485
TO BE ANSWERED ON 27.12.2017
RAILWAY PROJECTS IN MADHYA PRADESH
†1485. SHRI MANOHAR UTAWAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of various railway projects being undertaken in Madhya
Pradesh and the current status thereof, project-wise;
(b) the number of projects running behind schedule and the reasons
therefor, project-wise;
(c) the details of the cost overrun for delayed projects, project-wise; and
(d) the current status of the survey for a new railway line between Dewas
and Shajapur?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS
(SHRI RAJEN GOHAIN)
(a) to (d): A Statement is laid on the Table of the House.
*****
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED
QUESTION NO. 1485 BY SHRI MANOHAR UTAWAL TO BE ANSWERED IN
LOK SABHA ON 27.12.2017 REGARDING RAILWAY PROJECTS IN MADHYA
PRADESH
(a): At present, 36 projects consisting of 8 New Lines, 5 Gauge
Conversion and 23 Doublings falling partly or fully in the State of Madhya
Pradesh are in different stages of execution. Details of these projects are
as under:
(` in crore)
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
1.
Lalitpur-
Satna, Rewa-
Singrauli, &
Mahoba-
Khajuraho
541
1997-98
3500
1210
301
Lalitpur-Khajuraho-
Mahoba (229.5 km):
Commissioned.
Khajuraho-Panna
(70.55 km) & Sidhi-
Singrauli (78 km):
Land acquisition has
been taken up.
Panna-Satna (72.60
km): Earthwork and
minor bridges have
been taken up.
Satna-Rewa (50 km):
Existing BG rail line.
Rewa-Sidhi (88.75
km): Land between
Rewa-Govindgarh (20
km) has been
acquired. Earthwork,
works of minor/major
bridges have been
taken up.
2.
Ramganj
Mandi-
Bhopal
262
2000-01
2348
637
200
Ramganjmandi-
Jhalawar (26.5 km):
Commissioned.
Jhalawar-Nayagaon
(48 km): Earthwork,
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
minor/major bridges
works have been
taken up. Land
acquisition has been
completed upto km
165 except 10 km
between km 146 to
156.
Land acquisition in
remaining portion
has been taken up.
3.
Chhota
Udepur-Dhar
158
2007-08
1825
390
141
Chhota Udepur-
Motisadli (22.30 km):
CRS authorization
received for running
passenger trains.
Motisadli-Alirajpur
(26.40 km): Work is
at advance stage of
completion.
Alirajpur-Dhar (110
km): Land acquisition
has been taken up.
4.
Dahod-Indore
via
Sardarpur,
Jhabua &
Dhar (200.97
km)
including MM
for change in
alignment
via Amjhera
(4.82 km)
206
2007-08
1942
414
140
Indore-Tihi (20.42
km): Commissioned.
Tihi-Pithampur &
Jhabua-Sardarpur:
Earthwork, minor
bridge & tunnel
works have been
taken up.
Pithampur-Sagor
(9.12 km): Earthwork
& minor bridges work
have been taken up.
Sagor-Amjhera &
Pitol -Katwara: Land
acquisition has taken
up.
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
Jhabua-Pitol (14.66
km): Earthwork,
ROB/RUB works have
been taken up.
Katwara-Dahod
(11.32 km): Land
acquired. Earthwork
& all bridges work
completed. Ballast
supply & track
linking has been
taken up.
5.
Ratlam-
Dungarpur
via
Banswara
176
2011-12
3450
222
91
Project has been put
on hold as Govt. of
Rajasthan now
shown inability to
share cost of the
project.
6.
Indore-
Jabalpur
342
2016-17
4320
-
1
New work included in
Budget 2016-17
subject to requisite
Government
approvals.
7.
Indore-
Manmad via
Malegaon
368
2016-17
9968
-
150
New work included in
Budget 2016-17
subject to requisite
Government
approvals.
8.
Nimach-Badi
Sadri
48
2017-18
475
-
1
New work included in
Budget 2017-18
subject to requisite
Government
approvals.
1.
Jabalpur-
Gondia
including
Balaghat-
Katangi (285
300
1996-97
1544
1235
154
Gondia- Katangi
including MOIL
Limited siding (90
km) and Jabalpur--
Sukrimangela-
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
km) & MM
Katangi-
Tirodi New
Line (15 km)
Nainpur (113.59 km):
commissioned.
Nainpur-Balaghat (77
km): Earthwork,
minor/major bridges,
ROB, RUB, ballast
supply works have
been taken up.
Katangi-Tirodi (15
km) (New Line):
Forest clearances
received. Land
acquisition has been
taken up.
2.
Chhindwara-
Nagpur
150
2005-06
1101
998
181
Chhindwara-
Bhandarkund (34
km): CRS
authorization
received on
17.10.2017 to run
passenger trains.
Earthwrok,
minor/major bridges,
ROBs/RUBs,
tunneling works have
been taken up in
remaining portion.
3.
Ratlam-
Mhow-
Khandwa-
Akola
(472.64 km)
with new MM
Fatehabad-
Chandrawati
Ganj-Ujjain
(22.96 km)
496
2008-09
2265
955
320
Ratlam-Mhow (129
km): Commissioned.
Mhow-Sanawad
(76.12 km): Land
acquisition has been
taken up.
Sanawad-Khandwa
(63 km): Earthwrok,
minor/major bridges,
ROBs/RUBs & ballast
supply works have
been taken up.
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
Akola-Akot (43.50
km): Earthwrok,
minor/major bridges,
ROBs/RUBs & ballast
supply works have
been taken up.
Akot-Amlakhurd (78
km): Forest & wild
life clearance is
awaited.
Amlakhurd-Akola:
Project is at planning
stage.
Fatehabad-
Chandrawati Ganj-
Ujjain (22.96 km):
New MM sanctioned
in budget 2017-18.
4.
Chhindwara-
Mandla Fort
182
2010-11
816
353
182
Earthwork,
minor/major bridges,
ROBs/RUBs/LHS
works have been
taken up. Land
acquisition, tree
cutting permission in
small patches
required.
5.
Gwalior-
Sheopurkalan
with
extension to
Kota
284
2010-11
3845
36
75
Land acquisition has
been taken up.
1.
Bhopal-Bina
3
rd
line
145
2008-09
1200
1057
100
Project is at advance
stage of completion.
137 km length
already
commissioned.
2.
Budhni-
33
2010-11
992
53
2
Geological and Geo-
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
Barkhera 3
rd
line
Tech surveys have
been completed.
Forest clearance is
awaited.
3.
Bina-Kota
including MM
of Malkhedi
Mahadev
khedi.
283
2011-12
1486
398
125
103 km length in
patches is in
advance stage of
completion. Work has
been taken up in
balance portion.
4.
Barkhera-
Habibganj 3
rd
line
41
2012-13
327
77
50
Earthwork, minor
bridges and ballast
supply have been
taken up. Tree
cutting in the
alignment has been
taken up.
5.
Itarsi-Budhni
3
rd
line
26
2012-13
278
86
30
Earthwork, minor
bridges and ballast
supply have been
taken up. Contract
for Narmada Bridge
awarded &
construction of
substructure has
been taken up.
6.
Anuppur-
Katni 3
rd
line
166
2015-16
1371
400
95
Anuppur-Singhpur
(35.10 km) Singhpur
Badhwa Bara (15 km)
& Mudaria-Karkeli
(23 km) sections are
in advance stage of
completion.
7.
Bilaspur
(Pendra
Road)-
Anuppur 3
rd
line
50
2015-16
394
128
60
Tenders for all civil
works awarded.
Earthwork, ROB/RUB
work and ballast
supply works have
been taken up.
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
8.
Teegaon-
Chichonda
Ghat section
3
rd
line
17
2015-16
176
62
12
Land acquisition for
2.02 Ha., earthwork
and minor
bridges/RUB works
have been taken up.
9.
Itarsi-Nagpur
(Balance) 3
rd
line with
Dharakho-
Maramjhiri
Ghat section
3
rd
line
280
2015-16
2450
46
60
Work has been
combined with
Dharakho and
Maramjhiri Ghat 3
rd
line (13 km). FLS
completed. 50% Land
acquisition has been
taken up. Land
proposal for Nagpur-
Darimeta (92 km) has
been submitted to
State Govt.
Earthwork and minor
bridges works have
been taken up.
10.
Jhansi-Bina
3
rd
line
153
2015-16
2002
56
430
Earthwork,
minor/major bridges
works have been
taken up.
11.
Katni-Bina
3
rd
line
279
2015-16
2478
305
254
Earthwork,
minor/major bridges
works have been
taken up.
12.
Katni Grade
Separator
Bypass line
22
2015-16
582
20
200
Concept plans
approved. FLS has
been taken up.
13.
Katni-
Singrauli
261
2015-16
1763
377
225
Earthwork and minor
bridges works have
been taken up in
Katni-Beohari,
Marwasgram-
Singrauli, Katangi-
Khurd-Salhana and
deoragram-Maihdaiya
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
sections.
14.
Mathura-
Jhansi 3
rd
line
274
2015-16
3678
250
255
Works of minor and
major bridges have
been taken up.
15.
Nimuch-
Chittaurgarh
56
2015-16
390
20
80
Nimuch-
Shambhupura (44.12
km): Earthwork and
ballast supply have
been taken up.
Shambhupura-
Chittaurgarh (11.61
km): Earthwork,
major bridges work
and ballast supply
have been taken up.
16.
Ramna-
Singrauli
160
2015-16
2436
150
25
Ramna-
Wyndhamgank-
Dudhinagar (45.94
km): Tenders for
Earthwork, minor and
major bridges have
been awarded.
Dudhinagar-Singrauli
(110.39 km): Tender
for Earthwork and
minor bridges have
been awarded.
17.
Satna-Rewa
50
2015-16
403
40
43
Satna-Kaima (6 km):
Track linking has
been taken up.
Kaima-Baghai (24
km): Earthwork,
works of minor
bridges, track linking
and RUBs/LHS have
been taken up.
Baghai-Rewa (20
km): Earthwork,
minor bridges, major
S.
No.
Name of
Project
Length
(in km)
Year of
sanction
Latest
anti-
cipated
cost
Expen-
diture
upto
March,
2017
Outlay
2017-18
Present status
bridges & ballast
supply have been
taken up.
18.
Sontalai-
Bagratawa
patch
doubling
7
2015-16
96
44
40
FLS completed.
Earthwork and work
of Important bridges
of Tawa River &
minor bridges have
been taken up.
19.
Indore-
Dewas-Ujjain
80
2016-17
700
-
20
New work included in
Budget 2016-17
subject to requisite
Govt. approvals.
20.
Jhansi-
Khairar-
Manickpur &
Khairar
Bhimsen
411
2016-17
3000
-
10
New work included in
Budget 2016-17
subject to requisite
Govt. approvals.
21.
Jukehi Chord
line at Katni
1
2016-17
12
-
2
FLS completed. Land
acquisition has been
taken up. Earthwork,
works of minor
bridges, RUB & track
linking have been
taken up.
22.
Nagda-Ujjain
Doubling of
Gambhir
Bridge
1
2016-17
28
-
10
New work sanctioned
in 2016-17. Project is
at initial stage.
23.
Powarkheda-
Jujharpur
single line
flyover in up
direction
12
2016-17
247
116
10
Land acquisition has
been taken up. Joint
verification of land
for flyover done for
all 8 villages.
(b) & (c): Till 2013-14, due to overall limited availability of funds, most of
the projects were not progressing satisfactorily. Since 2014-15, based on
physical progress of projects, last mile connectivity projects and projects
for decongesting the existing routes have been given sufficient funds. For
this purpose, funds for capacity enhancement projects have been arranged
through institutional financing by tying up loan with M/s Life Insurance
Corporation of India Limited for `1.5 lakh crore for assured funding of viable
projects.
(d): There is an existing Broad Gauge line between Dewas and Shajapur.
*****