*This is an unreported opinion, and it may not be cited in any paper, brief, motion, or other
document filed in this Court or any other Maryland Court as either precedent within the
rule of stare decisis or as persuasive authority. Md. Rule 1-104.
Circuit Court for Howard County
Case No. 13-C-15-106114
UNREPORTED
IN THE COURT OF SPECIAL APPEALS
OF MARYLAND
No. 1222
September Term, 2020
______________________________________
H&H ROCK, LLC, t/a H&H ROCK
COMPANIES, et al.
v.
MORRIS & RITCHIE ASSOCIATES, INC.
______________________________________
Leahy,
Zic,
Sharer, J. Frederick,
(Senior Judge, Specially Assigned),
JJ.
______________________________________
Opinion by Sharer, J.
______________________________________
Filed: March 1, 2022
Unreported Opinion
*This is an unreported
This appeal arises out of a contract dispute between appellant, Morris & Ritchie
Associates (“MRA”), and appellees, H&H Rock, LLC t/a H&H Rock Companies (“H&H
Rock”), Rock Realty, Inc. (“Rock Realty”) (collectively, the Rock Companies”), and
Mark K. Levy, principal of the Rock Companies. Following a remand from this Court and
a bench trial, the circuit court entered judgment in favor of MRA. The Rock Companies
appealed that judgment and MRA filed a cross-appeal.
On appeal, the parties present multiple questions for our review, which we have
rephrased slightly:
1. Did the trial court err in finding that the Rock Companies were precluded,
on remand, from challenging the propriety of the claims in the First and
Second Amended Complaints?
2. Did the trial court err in finding the Rock Companies jointly and severally
liable as to Counts I and II of the Second Amended Complaint?
3. Did the trial court err in finding that Rock Realty was not jointly and
severally liable on Count III of the Second Amended Complaint?
4. Did the trial court err in awarding attorneys fees to MRA or in the
calculation of that award?
For the reasons set forth below, we affirm, in part, and remand for modification of
the order awarding attorney’s fees.
BACKGROUND
The background facts of this case were set forth in detail in this Court’s previous
unreported opinion, Morris & Ritchie Assocs., Inc. v. H&H Rock, LLC, No. 1824,
September Term 2016 (filed January 30, 2018) (“MRA I”):
MRA performed engineering and other services for appellees
pursuant to three proposals accepted by Mr. Levy, a principle of H&H Rock
Unreported Opinion
2
and Rock Realty. The first contract, (Proposal One - # 15129.02), which Mr.
Levy accepted on June 23, 2006, provided that MRA would be paid a lump
sum of $127,000.00, exclusive of any out-of-pocket expenses and “[a]ny
hourly work included in this proposal and extra work, which [MRA was]
requested to perform,” which would be billed at the hourly rates provided in
the proposal.
The second contract, (Proposal Two - # 15129.03), provided for
Surveying, Land Planning and Civil Engineering Services related to a
relocation of model homes for a lump sum fee of $114,100.00. Out-of-
pocket expenses and “[a]ny hourly work included in this proposal and extra
work, which [MRA was] requested to perform” would be billed at the hourly
rates set forth in the proposal.
The third contract, (Proposal Three - #15129.04), submitted on June
28, 2007, for Sketch Plan Services, provided for a lump sum fee of
$68,500.00, exclusive of out-of-pocket expenses. “Any hourly extra work”
that MRA was requested to perform would be billed at the hourly rates
provided.
Each of the proposals provided that billing would occur on a monthly
basis, with payment due 30 days after invoicing. The proposals also
incorporated MRA’s General Provisions, which stated, in pertinent part, as
follows:
8. PAYMENTS
Invoices will be submitted by MRA on a monthly basis as work
proceeds. Payments will be due and payable in full within thirty
(30) days of the date of invoice, without retainage, and will not be
contingent upon receipt of funds from third parties. In the event that
the Client objects to all or any portion of any invoice, the Client shall
notify MRA of the objection within fifteen (15) days from date of the
invoice, given reasons for the objection, and pay that portion of the
invoice not in dispute. If at any time, an invoice remains unpaid for a
period in excess of thirty (30) days, a service charge of one and one
half percent (1 1/2%) per month from the date of the invoice, an
effective maximum rate of eighteen percent (18%) per annum, will be
charged on past due accounts. If fees are not paid in full within thirty
(30) days of the due date, MRA reserves the right to pursue all
appropriate remedies, including stopping work and retaining all
documents without recourse. In the event a lien or suit is filed or
arbitration is sought to collect overdue payments under the
Unreported Opinion
3
Agreement, Client agrees to indemnify and hold harmless MRA from
and against any and all reasonable fees, expenses, and costs incurred
by MRA including but not limited to court costs, arbitrators and
attorney’s fees, and other claim-related expenses. In the event the
Client fails to pay any invoice in full, MRA shall have the right to
institute collection procedures. The Client shall be responsible for all
costs of collection including litigation costs, reasonable attorney’s
fees not to exceed 30% of the amount due, and court costs.
MRA sent invoices to the attention of Mr. Levy at the address
associated with H&H Rock. Each invoice identified the proposal number for
which the invoice was associated.
At the time the complaint was filed, MRA alleged that two invoices
submitted in 2010 for work performed pursuant to Proposal One, in the
amount of $705.68, remained unpaid. Twenty invoices for work performed
pursuant to Proposal Two, billed between 2007 and 2009, in the amount of
$129,058.48, remained unpaid. With respect to Proposal Three, 29 invoices,
billed between 2009 and 2014, in the amount of $208,440.38, remained
unpaid. MRA completed the services associated with the Proposals in 2014.
Id. at 2-4 (footnotes omitted).
Procedural History: MRA I
On December 18, 2015, MRA filed a complaint against the Rock Companies in the
Circuit Court for Howard County, alleging, inter alia, breach of contract for failure to make
payment on 51 invoices, issued between 2007 and 2014, for civil engineering services
provided pursuant to Contract .02, Contract .03 and Contract .04 (the “Contracts”). MRA
alleged that the Rock Companies had agreed to pay all outstanding charges by December
31, 2010, and that the Rock Companies had defaulted on this agreement. MRA further
Unreported Opinion
4
alleged that Mr. Levy subsequently acknowledged the debt to be due and promised
payment “to induce MRA into continuing to provide the [s]ervices[.]
1
The court granted partial summary judgment in favor of the Rock Companies,
finding that 46 of the 51 invoices were barred by the statute of limitations. The Rock
Companies then tendered payment for the amount owed on the remaining five invoices and
moved for summary judgment on the ground that MRAs remaining claims were moot.
Before the circuit court ruled on the second summary judgment motion, MRA filed
a First Amended Complaint, reasserting its breach of contract claims and adding two new
claims of detrimental reliance/promissory estoppel and fraud, and adding Mr. Levy as a
defendant.
That same day, MRA filed its opposition to the motion for summary judgment.
MRA asserted that the Rock Companies “acknowledged and promised to pay all
outstanding debts” and presented affidavits, documents, and deposition testimony in
support.
The Rock Companies moved to strike the First Amended Complaint, arguing that
MRA was precluded from amending its complaint to add new claims in circumvention of
the circuit court’s summary judgment order. The trial court denied the Rock Companies’
1
In the instant case, Contract .02 was submitted by MRA to Rock Realty, Inc.,
attention Mark L. Levy, who executed the contract as “President” purportedly on behalf of
Rock Realty, Inc. Contract 0.3 was also submitted by MRA to Rock Realty Inc., attention
Mark L. Levy, who executed the contract as “President” purportedly on behalf of Rock
Realty, Inc. Contract .04 was submitted by MRA to H&H Rock Companies, attention
Mark Levy, who executed this contract as “President” purportedly on behalf of H&H Rock
Companies.
Unreported Opinion
5
Motion to Strike. Mr. Levy moved to dismiss the First Amended Complaint, or in the
alternative, for summary judgment. After a hearing on the motions for summary judgment,
the court granted summary judgment in favor of the Rock Companies and Mr. Levy on all
counts in the First Amended Complaint. MRA appealed this judgment.
First Appeal
In MRA I, MRA argued that the trial court had erred in entering partial summary
judgment on limitations grounds because its claims did not accrue until the completion of
its services in 2014. MRA I, slip op. at 32. In an unreported opinion, this Court affirmed
the circuit court’s grant of partial summary judgment in the May 4, 2016 order, holding
that the limitations period on MRA’s claims for breach of contract began to run on the date
each invoice was due, not when the services were completed. Id. at 33. We held that the
trial court properly granted partial summary judgment on limitations grounds as to MRA’s
claims for 46 of the 51 invoices because MRA had failed to argue in the initial summary
judgment proceedings that the limitations period was tolled by an acknowledgement of the
debt. Id. at 34-42.
With respect to the circuit court’s full grant of summary judgment on the First
Amended Complaint, we affirmed the circuit court’s ruling as to MRA’s claims for
detrimental reliance and fraud. Id. at 53-56. As to the breach of contract claim in the First
Amended Complaint, we held that the circuit court had erred in granting summary
judgment because “[w]hether there was an acknowledgment(s) that tolled the statute of
limitations on the invoices that have not been paid is a question for the trier of fact.” Id. at
50. In making this determination, we noted:
Unreported Opinion
6
The parties do not address on appeal the propriety of realleging, in an
amended complaint, claims on which summary judgment has already been
granted. In the circuit court, however, the [Rock Companies] did move to
strike the amended complaint. They asserted, among other things, that the
court had already ruled in their favor on the claims that accrued prior to
December 18, 2012, and MRA was “not entitled to circumvent the Court’s
adjudication of its claims by filing the First Amended Complaint, in which it
completely disregards the Court’s prior rulings.” The circuit court denied
that motion, and [the Rock Companies] do not challenge that ruling in their
brief. Accordingly, the propriety of the amended complaint realleging claims
that already had been ruled upon is not before us. Rather, the issue presented
is whether the circuit court properly granted summary judgment on the
amended complaint. See Gonzales v. Boas, 162 Md. App. 344, 355
(“[A]mended complaint supercedes the initial complaint,” rendering the
amended complaint the operative pleading in this case), cert. denied, 388,
Md. 405 (2005).
Id. at 48. We further noted that the “procedural posture” of the case when the circuit court
granted summary judgment on the First Amended Complaint was “significantly different.
Id. We referenced the additional allegations in the First Amended Complaint and,
contrasting the “lack of evidence produced during the initial motion[,]noted affidavits
and documents regarding whether there was an “acknowledgment of the debt that tolled
the statute of limitations.” Id. at 48-49. Accordingly, we remanded the case “for further
proceedings on Count I of the First Amended Complaint.” Id. at 56.
Proceedings on Remand
After remand, the Rock Companies filed a motion for reconsideration of the motion
to strike and for summary judgment. The circuit court denied both motions, respectively.
On October 26, 2018, MRA filed a Second Amended Complaint, which divided its
breach of contract claim into three counts predicated on the three Contracts. On July 8,
2019, the Rock Companies filed a motion for reconsideration of the motion for summary
Unreported Opinion
7
judgment. Following the trial, the court denied the Rock Companies’ motion for
reconsideration.
During the two-day bench trial, MRA presented evidence largely unrebutted by the
Rock Companies concerning the outstanding invoices, whether Mr. Levy acted on behalf
of Rock Realty and H&H Rock, and the relationship between the Rock Companies. MRA
presented evidence demonstrating that Mr. Levy had multiple discussions and exchanged
various correspondence with MRA relating to the debt under the three Contracts.
Specifically, between 2010 and 2013, Mr. Levy made various promises to pay the
outstanding invoices, including a February 24, 2010 letter agreement, directed to H&H
Rock Companies, which identified the three Contracts. The letter agreement provided that
Mr. Levy acknowledge[d] and agree[d] that the outstanding invoices and charges included
in the statement of account are fair and reasonable charges for the services
satisfactor[ily] performed by MRA and that H&H Rock owes all amounts as shown
therein. Likewise, on April 18, 2013 and in May 2013, Mr. Levy and Frank Hertsch,
MRA’s president, discussed the outstanding invoices, first at a scheduled meeting and then
at a chance encounter at an industry meeting in Las Vegas. In both instances, according to
the trial testimony of MRA’s witnesses, Mr. Levy assured Mr. Hertsch that MRA would
be paid.
At the conclusion of MRA’s case-in-chief, the Rock Companies moved for
judgment. Specific to this appeal, the Rock Companies contended that judgment was
appropriate because MRA could not circumvent the May 4, 2016 partial summary
Unreported Opinion
8
judgment order by filing an amended complaint, and that the complaint identified the
wrong entities. In its ruling from the bench, the court determined, in pertinent part:
The [c]ourt is persuaded that the balance tips in favor of the law of the
case precluding the [Rock Companies] from relying on the earlier summary
judgment ruling and I point specifically to that quote from the Court of
Special Appeals with respect to the propriety of challenging the amended
complaint. I think that is preclusive here. . . . I think what happened was the
[Rock Companies] essentially waived that argument by failing to raise it on
- - on the appeal . . . . And failure to do so under the law of the case doctrine,
I believe, rules that argument out at this time.
After this ruling, Thomas Gessner, the chief financial officer for H&H Rock and the only
witness for the Rock Companies, testified to the relationship between H&H Rock and Rock
Realty. According to Mr. Gessner, H&H Rock and Rock Realty were separate companies,
sharing a common owner, Mr. Levy. The Rock Companies then rested.
Following requested post-trial briefing, the court issued a memorandum decision
and order. In [a]ddressing the primary issue[] raised by remand,” the court found “that
MRA indeed proved that [the Rock Companies]’ acknowledgment of their debts was
unqualified, clear and distinct, satisfying the requisite legal standard.” The court
referenced the 2010 letter agreement, the April 2013 meeting, and May 2013 encounter in
Las Vegas to find that “Mr. Levy fended off MRA collecting payment by repeatedly
acknowledging the debts, promising to pay what was owed.” Regarding the relationship
between the Rock Companies, the court found:
H&H Rock and Rock Realty were not materially different entities, at least as
conveyed to MRA by H&H Rock and Mr. Levy. [MRA] operated under the
reasonable assumption that the two were essentially interchangeable, as one
executive, Mr. Levy, represented both, and a 2007 letter announced that the
companies had merged. Each of the invoices admitted in evidence was
directed to H&H Rock Companies. No evidence indicates that Mr. Levy or
Unreported Opinion
9
his companies ever suggested these bills were misdirected. To the contrary,
H&H Rock Companies proclaimed that Rock Realty and H&H Rock had
been folded into H&H Rock Companies. When Mr. Levy executed the 2010
letter agreement, he did so on behalf of Rock Realty and H&H Rock
Companies. And Mr. Levy continued to act on behalf of each of these entities
in his dealings with MRA. Certainly, [the Rock Companies] did nothing to
disabuse MRA of the notion that Mr. Levy acted on their behalf.
Mr. Levy acted as an agent on behalf of Rock Realty and H&H Rock.
With respect to the first two contracts, he, along with the 2007 letter,
conveyed apparent authority that H&H Rock assumed the obligations of
Rock Realty. As to the third contract, however, evidence did not establish
that Rock Realty assumed the obligations and duties of H&H Rock. Rock
Realty therefore cannot be held jointly and severally liable on the third
contract.
The court entered judgment in favor of MRA in the amount of $1,283.43 on Count I
(Contract .02); $153,463.81 on Count II (Contract .03); and $243,757.37 on Count III
(Contract .04), plus pre-judgment interest, post-judgment interest, costs, and reasonable
attorney’s fees. MRA sought an application for attorney’s fees, and the court granted
attorney’s fees at 30% of the judgment as to each count, and additional fees at the per diem
rate of $0.11 on each count from July 16, 2020 through December 4, 2020. After the Rock
Companies noted an appeal, MRA noted a cross-appeal.
DISCUSSION
I.
The Rock Companies’ Challenge to the First and Second Amended Complaints
A. Parties’ Contentions
The Rock Companies contend that the “trial court erred in failing to hold that [MRA]
was precluded from circumventing the May 4, 2016 Order by filing the First and Second
Amended Complaints” in two respects. First, the Rock Companies contend that the “trial
Unreported Opinion
10
court erred in holding that the law of the case doctrine precluded [the Rock Companies]
from challenging the propriety of [MRA]’s attempt[] to circumvent the May 4, 2016 Order
by filing the First and Second Amended Complaints.” According to the Rock Companies,
“Maryland appellate courts have not expressly addressed the application of the Waiver
Rule when an appellee declines to raise an issue on appeal.” Relying on federal case law,
the Rock Companies assert:
Imposing an obligation to raise every conceivable alternative ground for
affirmance places an appellee at a procedural disadvantage since the appellee
will not have an opportunity to reply to any response set forth by the
appellant. Moreover, requiring an appellee to raise every basis for
affirmance defeats the purpose of the law of the case doctrine. Rather than
facilitate judicial efficiency, addressing every possible contingency would
overburden appellate courts with numerous tangential issues. As the Court
held in Crocker v. Piedmont Aviation, Inc., 49 F.3d 735 (D.C. Cir. 1995), a
degree of leniency should be used in applying the Waiver Rule to appellees.
Further, the Rock Companies assert that the law of the case doctrine is “inapplicable to
issues that arise after a case is remanded by the appellate court.” After the filing of the
Second Amended Complaint, “the law of the case doctrine no longer precluded [the Rock
Companies] from challenging the propriety of [MRA]’s attempt to circumvent this Court’s
prior Order.”
Second, the Rock Companies contend that MRA was “not entitled to ignore a
court’s ruling and force another party to re-litigate claims by filing an amended complaint.”
According to the Rock Companies, the “trial court erred in permitting the trial to proceed
and failing to grant [the Rock Companies]’s Motion for Judgment since [MRA]’s claims
were moot as a result of the May 4, 2016 Order.”
Unreported Opinion
11
In opposition, MRA asserts that the “circuit court acted within its discretion in
denying [the Rock Companies] many requests for reconsideration of its ruling on the
motion to strike.” According to MRA, the Rock Companies must not only establish that
the court erred in applying the law of the case doctrine but also “show that it was not
harmless[.]
To MRA, the “circuit court acted well within its discretion in denying all of the
[Rock Companies]’ post-remand motions because, inter alia, the law of the case doctrine
prevented it from reconsidering its ruling on the original Motion to Strike.” Relying on
Fidelity-Baltimore Nat.’l Bank & Tr. Co. v. John Hancock Mut. Life Ins. Co., 217 Md. 367,
372 (1958), MRA asserts that “questions that were decided, as well as those that could
have been raised and decided,’ are ‘not available to be raised in a subsequent appeal.’”
Because the Rock Companies could have raised this issue without filing a cross-appeal and
could have moved for a motion to reconsider or petitioned for further review before the
Court of Appeals, “the law of the case . . . foreclosed [the Rock Companies]’ right to further
challenge the circuit court’s denial of their Motion to Strike.” MRA argues that a straight-
forward application of Maryland law “requires” affirmance of the judgment and asserts
that there is a “noticeable difference” in Maryland’s law of the case doctrine and its federal
counterpart.
Alternatively, MRA avers that the Rock Companies “cannot prevail in this appeal
because they cannot demonstrate that the circuit court abused its discretion in denying the
Motion to Strike or any of the various motions for reconsideration of the same.” To MRA,
reconsideration of the court’s summary judgment order was “well within the circuit court’s
Unreported Opinion
12
discretion, but it was also consistent with Maryland law, which favors allowing
amendments that result in resolution of claims on their merits, rather than on procedural
technicalities.”
Finally, in response to the Rock Companies’ argument that the Second Amended
Complaint revived their objection, MRA argues that the law of the case doctrine bars
consideration of issues, not simply pleadings or motions.
B. Law of the Case
Whether the law of the case doctrine should be applied in particular circumstances
is a legal question; accordingly, we review a lower court’s invocation of that doctrine
without any special deference. Baltimore Cnty. v. Fraternal Ord. of Police, Baltimore
Cnty. Lodge No. 4, 449 Md. 713, 731 (2016).
The Court of Appeals has explained that the law of the case doctrine is one of
appellate procedure, and that, “[u]nder the doctrine, once an appellate court rules upon a
question presented on appeal, litigants and lower courts become bound by the ruling, which
is considered to be the law of the case.” Scott v. State, 379 Md. 170, 183 (2004). “Not
only are lower courts bound by the law of the case, but ‘[d]ecisions rendered by a prior
appellate panel will generally govern the second appeal’ at the same appellate level as well,
unless the previous decision is incorrect because it is out of keeping with controlling
principles announced by a higher court and following the decision would result in manifest
injustice.” Id. at 184 (quoting Hawes v. Liberty Homes, 100 Md. App. 222, 231 (1994)).
In Maryland, the law of the case doctrine “applies to both questions that were
decided and questions that could have been raised and decided.” Holloway v. State, 232
Unreported Opinion
13
Md. App. 272, 282 (2017). In the leading case of Fidelity-Baltimore National Bank &
Trust Co. v. John Hancock Mutual Life Insurance Co., the Court instructed:
It is the well-established law of this state that litigants cannot try their
cases piecemeal. They cannot prosecute successive appeals in a case that
raises the same questions that have been previously decided by this Court in
a former appeal of that same case; and, furthermore, they cannot, on the
subsequent appeal of the same case raise any question that could have been
presented in the previous appeal on the then state of the record, as it existed
in the court of original jurisdiction. If this were not so, any party to a suit
could institute as many successive appeals as the fiction of his imagination
could produce new reasons to assign as to why his side of the case should
prevail, and the litigation would never terminate. Once this Court has ruled
upon a question properly presented on an appeal, or, if the ruling be contrary
to a question that could have been raised and argued in that appeal on the
then state of the record, as aforesaid, such a ruling becomes the ‘law of the
case’ and is binding on the litigants and courts alike, unless changed or
modified after reargument, and neither the questions decided nor the ones
that could have been raised and decided are available to be raised in a
subsequent appeal.
Fidelity-Baltimore Nat. Bank & Tr. Co., 217 Md. at 371-72.
The Rock Companies assertion that “Maryland courts have not expressly addressed
the application of the Waiver Rule when an appellee declines to raise an issue on appeal[,]
lacks merit, as John Hancock is directly on point on this issue. There, an employee of John
Hancock presented false insurance claims to the company on behalf of fictitious payees.
Id. at 370. John Hancock issued checks for these claims, which were forwarded to the
employee, who then forged the endorsements of the fictitious claimants on the back of each
check, deposited the checks in several banks, and thereafter withdrew the money. Id. John
Hancock learned of the fraud and eventually brought suit against the collecting banks for
honoring the forged checks. Id. The trial court dismissed the complaint on the pleadings.
On appeal, the Court of Appeals reversed, and held that the stipulation of facts by the
Unreported Opinion
14
parties entitled John Hancock to summary judgment. Id. at 371. On remand, the trial court
entered summary judgment in favor of John Hancock Mutual. Id.
On a second appeal, the collecting banks raised two questions: first, whether a
collecting bank is liable to the drawer of a check issued to a fictitious payee if the drawer
is unaware of the fictitious payee and the check bears a fraudulent endorsement; and
second, whether the “imposter rule” barred John Hancock Mutual from recovery. Id. As
to the first question, the Court of Appeals explained this question was raised in the first
appeal and was specifically answered. As to the “imposter rule” defense, the court
explained that although this issue was not raised in the previous appeal, there was “no doubt
that it was available in that proceeding as a ground to sustain the demurrers, if it be
available here to defeat the judgments obtained by the appellee.” Id. As a result, the Court
held that both issues had already been settled in John Hancock, the first appeal, under the
law of the case doctrine. Id. at 372.
We have further clarified that “under the law of the case doctrine, litigants cannot
raise new defenses once an appellate court has finally decided a case if these new defenses
could have been raised based on the facts as they existed prior to the first appeal.” Schisler
v. State, 177 Md. App. 731, 745 (2007); see also Davis Sand & Gravel Corp. v.
Buckler, 231 Md. 370, 373-74 (1963) (holding defendant that won at trial on issue of
whether it had right to use easement, but then lost on appeal, could not on remand raise the
issue of whether damages were proved at trial when this question could have been raised
on a motion for reargument).
Unreported Opinion
15
While the Rock Companies purport to rely on federal cases interpreting the law of
the case doctrine, we have recently recognized the “noticeable difference” between our
doctrine and the federal counterpart. Holloway, 232 Md. App. at 282. “In Maryland, the
law of the case doctrine applies to both questions that were decided and questions that
could have been raised and decided[,] while “[u]nder federal law, the law-of-the-case
doctrine only applies to issues the court actually decided.” Id. (citation and internal
quotation marks omitted).
Further, there was nothing precluding the Rock Companies from presenting the
denial of their motion to strike as an alternative basis to affirm the court’s judgment. We
also recognize that “[w]here a party has an issue resolved adversely in the trial court, but
receives a wholly favorable judgment on another ground, that party may, as an appellee
and without taking a cross-appeal, argue as a ground for affirmance the matter that was
resolved against it at trial. This is merely an aspect of the principle that an appellate court
may affirm a trial court’s decision on any ground adequately shown by the record.” Offutt
v. Montgomery Cnty. Bd. of Educ., 285 Md. 557, 564 n.4 (1979) (citations omitted).
We perceive no error in the circuit court’s determination that the law of the case
doctrine precluded the Rock Companies from relying on the May 4, 2016 order to challenge
the propriety of the First and Second Amended Complaints. Contrary to the Rock
Companies’ suggestion, the May 4, 2016 partial summary judgment order was not the
controlling or dispositive order in the case, as that order and the full summary judgment
order, were reviewed in MRA I. This Court’s decision that the Rock Companies had waived
their challenge to the propriety of the First Amended Complaint by failing to raise that
Unreported Opinion
16
issue on appeal constituted the law of the case. Once an appellate court has answered a
question of law in a given case, the issue is settled for all future proceedings. Stokes v.
Am. Airlines, Inc., 142 Md. App. 440, 446 (2002). The law of the case doctrine “prevents
trial courts from dismissing appellate judgment and re-litigating matters already resolved
by the appellate court” in a case involving the same parties and the same claims. Id. The
law of the case doctrine precludes us from considering in this appeal the propriety of
MRA’s amendment of claims following entry of the May 4, 2016 order, as the Rock
Companies could have, and should have, raised that issue in MRA I.
C. Mootness
The Rock Companies further assert that MRA’s claims were moot because “[t]he
May 4, 2016 Order remained the controlling dispositive ruling on [MRA]’s claims” and
neither this Court nor the trial court were bound by this Court’s opinion “without
considering the propriety of the attempt[] to circumvent an order by filing an amended
complaint.”
A case is considered moot when “‘past facts and occurrences have produced a
situation in which, without any future action, any judgment or decree the court might enter
would be without effect.’” La Valle v. La Valle, 432 Md. 343, 351 (2013) (quoting Hayman
v. St. Martin’s Evangelical Lutheran Church, 227 Md. 338, 343 (1962)). “The test for
mootness is ‘whether, when it is before the court, a case presents a controversy between
the parties for which, by way of resolution, the court can fashion an effective remedy[.]’”
Hamot v. Telos Corp., 185 Md. App. 352, 360 (2009) (quoting Adkins v. State, 324 Md.
641, 646 (1991)).
Unreported Opinion
17
While the Rock Companies argue that MRA’s claims were moot due to the May 4,
2016 Order, the evidence submitted in opposition to summary judgment and at trial
supports that the limitations period was tolled and would restart anew with each
acknowledgment of the debt. The Court of Appeals has explained this principal on multiple
occasions:
The statute of limitations does not extinguish the debt; it bars the
remedy only. Thus, Maryland law has long recognized that
acknowledgement of a debt barred by limitations removes the bar to pursuing
the remedy. An acknowledgement, sufficient to remove the bar of
limitations, need not expressly admit the debt, it need only be consistent with
the existence of the debt. Nor must it be an express promise to pay a debt;
just as an express promise to pay a debt barred by limitations revives the
remedy, “a mere acknowledgement of such a debt will remove the bar of the
statute, because if the debtor acknowledges the debt it is implied that he
promises to pay.” An acknowledgement of a debt can occur prior to the
running of limitations, in which event, rather than removing the bar of
limitations, it both tolls the running of limitations and establishes the date of
the acknowledgment as the date from which the statute will now run.
Jenkins v. Karlton, 329 Md. 510, 531 (1993) (citations omitted). Thus, the May 4, 2016
Order did not extinguish MRA’s claims for the first 46 invoices; it simply operated to bar
MRA’s remedy for those claims. Once MRA established Mr. Levy’s acknowledgement of
the debt, the bar to MRA’s remedy for its claims was removed. Accordingly, MRA’s
claims were not mooted by the May 4, 2016 Order.
II.
Joint and Several Liability
The Rock Companies challenge that they were joint and severally liable for Counts
I and II, and MRA challenges the court’s finding that Rock Realty was not liable on Count
III.
Unreported Opinion
18
The circuit court concluded that the 2010 Agreement constituted a modification of
the interest rate as to Contracts .02 and .03 in exchange for assurances of payment. The
court determined that the Rock Companies had failed to provide evidence showing that the
parties had agreed to form a new contract with the intent to replace the existing one,
sufficient to establish a novation.
With respect to Contracts .02 and .03, the court found that Mr. Levy had conveyed
apparent authority that H&H Rock had assumed the obligations of Rock Realty. As to
Contract .04, however, the court found that the evidence did not establish that Rock Realty
had assumed the obligations and duties of H&H Rock, and therefore, Rock Realty was not
jointly and severally liable on the third contract.
A. Parties’ Contentions
The Rock Companies aver that the circuit court erred in holding that the Rock
Companies were jointly and severally liable for Contracts .02 and .03. According to the
Rock Companies, the “most reasonable interpretation of [the] 2010 Agreement that would
allow the court to find a clear and unequivocal acknowledgment of the debt is that such
Agreement constituted a novation.” However, the Rock Companies argue that the 2010
Agreement did not meet the requirements for a novation. Further, the Rock Companies
assert that the 2010 Agreement could not constitute an amendment because “Rock Realty
did not execute the 2010 Agreement.”
In response, MRA asserts that the Rock Companies are “jointly and severally liable
under all three contracts.” According to MRA, “due to Levy’s own promises and actions,
MRA reasonably believed that Levy was authorized to act and was acting on behalf of
Unreported Opinion
19
Rock Realty when conducting business under the H&H Rock Companies trade name
registered to H&H.” In light of this conclusion, MRA argues that the court erred in
“concluding Rock Realty was not liable on Count III.” Finally, MRA surmises that the
Rock Companies “have not demonstrated how the circuit court committed reversible error
in deeming the 2010 Agreement an amendment” and, in any event, there is “ample evidence
supporting the circuit court’s conclusion not challenged on appeal that Mr. Levy
acted on behalf of both H&H and Rock Realty in executing the 2010 Agreement and
acknowledging [the Rock Companies]’ liability for the Outstanding Invoices in 2013.”
B. Analysis
The Court of Appeals summarized the characteristics of a novation in I. W. Berman
Properties v. Porter Brothers:
A ‘novation’ is a new contractual relation made with intent to
extinguish a contract already in existence. It contains four essential
requisites: (1) A previous valid obligation; (2) the agreement of all the parties
to the new contract; (3) the validity of such new contract, and (4) the
extinguishment of the old contract, by the substitution of the new one.
For a novation to exist there must be (evidence of) an agreement
among the parties to extinguish the old obligation(s) and substitute a new one
for it.
A novation is never presumed; the party asserting it must establish
clearly and satisfactorily that there was an intention, concurred in by all the
parties, that the existing obligation be discharged by the new obligation. . . .
The intention to substitute a new agreement for a previous contract
need not be expressed however, since facts and circumstances surrounding
the transaction, as well as the subsequent conduct by the parties, may show
such an acceptance as clearly as an express agreement; but such facts and
circumstances, when shown, must be such to establish that the intention to
work a novation is clearly implied.
276 Md. 1, 7-8 (1975) (cleaned up).
Unreported Opinion
20
Unlike a novation, a contract modification occurs when the parties mutually consent
to modifying certain terms of a contract. See L & L Corp. v. Ammendale Normal Inst., 248
Md. 380, 384 (1968). For example, parties may agree to change the terms of a contract “as
a compromise of their differences.” Freeman v. Stanbern Const. Co., 205 Md. 71, 78
(1954). In a case where “such differences arise out of a contract, a compromise of their
differences and the mutual agreement of the parties to vary the terms of the contract and to
enter into a new agreement embodying the compromise constitute sufficient consideration
to support the new agreement.” Id. (citing Hercules Powder Co. v. Harry T. Campbell
Sons Co., 156 Md. 346, 362 (1929)).
The extent to which an entity may be jointly or severally liable to a third party often
depends upon the actions of the entity’s agent. Agency principles have been summarized
on many occasions by our appellate Courts:
In an agency relationship, one person, the principal, can be legally bound by
actions taken by another person, the agent. An agency relationship is created
when the principal confers actual authority on the agent. Actual authority to
do an act can be created by written or spoken words or other conduct of the
principal which, reasonably interpreted, causes the agent to believe that the
principal desires him so to act on the principals account. Actual authority
may be inferred from conduct, including acquiescence. In the absence of
actual authority, a principal can be bound by the acts of a purported agent
when that person has apparent authority to act on behalf of the principal.
Apparent authority results from certain acts or manifestations by the alleged
principal to a third party leading the third party to believe that an agent had
authority to act. We have explained, however, that it is nearly axiomatic that
one dealing with an agent must use reasonable diligence and prudence to
ascertain whether the agent acts within the scope of his powers.
Dickerson v. Longoria, 414 Md. 419, 441-42 (2010) (cleaned up). In addition, an agency
by estoppel may arise “where the principal, through words or conduct, represents that the
Unreported Opinion
21
agent has authority to act and the third party reasonably relies on those representations.”
Johns Hopkins Univ. v. Ritter, 114 Md. App. 77, 96 (1996).
Here, the evidence supported the circuit court’s findings regarding joint and several
liability. First, there was ample support in the record for the circuit court’s conclusion that
Mr. Levy was conducting business with MRA on H&H’s behalf. This evidence included
the 2007 letter announcing the purported merger, the invoices directed to H&H Rock
Companies, and Mr. Levy’s execution of the 2010 letter agreement on behalf of H&H
Rock.
Second, Mr. Levy acted as an agent on behalf of Rock Realty and H&H. As the
court correctly concluded, the 2007 letter conveyed that H&H had assumed the obligations
of Rock Realty. Whether, in fact, this statement was accurate was not dispositive for
establishing H&H’s liability. An agent need not have actual authority to bind an entity if
the evidence shows that the agent had apparent authority and the third party had a basis for
reasonably relying on the actions of the agent. See Atl. Richfield Co. v. Sybert, 51 Md.
App. 74, 84 (1982) (explaining that apparent authority arises where a third party can prove
that the agent’s actions in entering an agreement gave rise to apparent authority to act on
behalf of the principal and the third party’s reliance on such actions was reasonable).
It also appears that Mr. Levy’s actions, summarized above, evidenced an intent to
affirm the Contracts and the obligations on behalf of H&H Rock. See Smith v. Merritt
Savings and Loan, Inc., 266 Md. 526, 536-40 (1972) (summarizing requirements for
ratification of a contract). Although H&H Rock was not an original signatory to Contract
.04, the evidence supported the circuit court’s conclusion that the 2010 Letter Agreement
Unreported Opinion
22
constituted a modification of the existing Contracts rather than a novation. As the circuit
court noted, the 2010 Letter Agreement modified the terms of the Contracts because it
“acknowledged the debt and gave H&H Rock Companies additional time to pay the
outstanding invoices. It also reduced the interest rate charged under the invoices to eight
percent on outstanding amounts due from the date of the letter.”
Based upon our review of the record, we agree with the circuit court’s determination
that there was no “credible evidence” to support the Rock Companies’ contention “that the
2010 letter agreement extinguished the prior existing agreements for all three contracts in
their entirety and created a completely new and distinct obligation.” The evidence
supported the circuit court’s conclusion that Mr. Levy, acting as an agent on behalf of H&H
Rock, conveyed that H&H Rock had assumed the obligations of Rock Realty, including
liability for Contracts .02 and .03. While Rock Realty remained liable as a signatory under
Contracts .02 and .03, MRA presented no evidence demonstrating that Rock Realty had
assumed the obligations of H&H Rock. Accordingly, we perceive no error in the circuit
court’s determination that Rock Realty remained liable as to Contracts .02 and .03, but that
Rock Realty had not assumed joint and several liability for H&H Rock’s obligations on
Contract .04.
III.
Attorney’s Fees
A. Parties’ Contentions
The Rock Companies contend that [t]he trial court also erred by awarding total
attorney’s fees in the amount of $127,690.17” for two primary reasons. “First, neither the
Unreported Opinion
23
subject Contracts nor the General Provisions attached thereto provide that the ‘amount due’
included interest.” According to the Rock Companies, [l]ogic dictates the ‘amount due’
denotes the principal amount due.” Otherwise, if daily interest were included, such
position would permit a greater award of attorney’s fees predicated upon the mere passage
of time, as opposed to the value of goods or service in dispute in the litigation or the work
reasonably required by an attorney.” Second, the Rock Parties contend that MRA’s
calculation is flawed because the parties’ “course of performance establishes that [MRA]
did not conceive of the ‘amount due’ as the aggregate of the principal amount due and
accrued interest.” According to the Rock Companies, with the exception of a statement
prepared by MRA’s counsel for trial, “the record is devoid of any evidence indicating that
[the] parties conceived of ‘amount due’ as the aggregate of the principal amount due and
accrued interest.”
In opposition, MRA asserts that “[i]nterest was part of the amount due under the
Contracts.” According to MRA, the “circuit court confronted two, completely distinct
questions: (a) determining the ‘amount due’ under the Contracts, and (b) determining
whether MRA incurred reasonable fees in excess of that amount.” MRA asserts that the
language of the Contracts is unambiguous and that “[p]ayment of an invoice ‘in full’
requires payment of both the outstanding principal and interest.” Turning to parol
evidence, MRA contends that this Court is unable to consider parol evidence to “vary, alter,
or contradict a contract that is complete and unambiguous,” Maslow v. Vanguri, 168 Md.
App. 298, 319 (2006) (citation and quotation marks omitted), and “even if this Court were
to consider the parties’ course of performance, it is of no help to [the Rock Companies].”
Unreported Opinion
24
Finally, MRA asserts that “[t]here is nothing unjust about the fact that, as [the Rock
Companies] failed to pay MRA, the contractual cap on reasonable attorneys’ fees increased
in proportion with the total amount due.”
In reply, the Rock Companies contend that the General Provisions of the Contracts
distinguish between “invoices” and “past due accounts.”
B. Analysis
This Court reviews “a court’s establishment of a ‘reasonable’ fee under an abuse of
discretion standard.” Garcia v. Foulger Pratt Dev., Inc., 155 Md. App. 634, 671 (2003).
It is clear that “[c]ontract clauses that provide for the award of attorney’s fees generally are
valid and enforceable in Maryland, subject to a trial court’s examination of the prevailing
party’s fee request for reasonableness.” Nova Rsch., Inc. v. Penske Truck Leasing Co., 405
Md. 435, 447-48 (2008) (citation omitted). The interpretation of a written contract is
reviewed de novo. Id. at 448.
In resolving the fee provisions in the Contracts, we recognize the oft-stated principal
that “Maryland applies an objective interpretation of contracts”:
If a contract is unambiguous, the court must give effect to its plain meaning
and not contemplate what the parties may have subjectively intended by
certain terms at the time of formation. A contract is ambiguous if, when read
by a reasonably prudent person, it is susceptible of more than one meaning.
In interpreting a contract provision, we look to the entire language of the
agreement, not merely a portion thereof. When interpreting a contract’s
terms, we consider the customary, ordinary and accepted meaning of the
language used.
Id. (internal citations and quotation marks omitted).
Here, Section 8 of the General Provisions of the Contracts provides, in relevant part:
Unreported Opinion
25
If at any time, an invoice remains unpaid for a period in excess of thirty (30)
days, a service charge of one and one half percent (1 1/2%) per month from
the date of the invoice, an effective maximum rate of eighteen percent (18%)
per annum, will be charged on past due accounts. If fees are not paid in full
within thirty (30) days of the due date, MRA reserves the right to pursue all
appropriate remedies, including stopping work and retaining all documents
without recourse. In the event a lien or suit is filed or arbitration is sought to
collect overdue payments under the Agreement, Client agrees to indemnify
and hold harmless MRA from and against any and all reasonable fees,
expenses, and costs incurred by MRA including but not limited to court costs,
arbitrators and attorneys fees, and other claim-related expenses. In the event
the Client fails to pay any invoice in full, MRA shall have the right to institute
collection procedures. The Client shall be responsible for all costs of
collection including litigation costs, reasonable attorney’s fees not to exceed
30% of the amount due, and court costs.
(Emphasis added.)
In this case, the contract was not ambiguous. First, the phrase amount due” is
unqualified. Customary meaning of the term “amount due” includes applicable interest as
well as the principal. See Eidelman v. Walker & Dunlop, Inc., 265 Md. 538, 545 (1972)
(“Interest is recoverable as of right upon a contract to pay money upon a day certain.”);
I.W. Berman Props., 276 Md. at 16 (same). Second, in the context of the language of
Section 8 of the General Provisions of the Contracts, “amount due” appears after language
regarding overdue invoices and the calculation of interest, suggesting that the amount due
applied to all costs, including interest, incurred as a result MRA’s efforts to collect unpaid
invoices. See, e.g., Weichert Co. of Maryland v. Faust, 191 Md. App. 1, 7 (2010) (“When
we interpret a contract, we must examine the contract as a whole, in order to determine the
intention of the parties.”). The clear language of the Contracts provided that interest
accrued on past due invoices after a period of thirty days. The circuit court’s determination,
Unreported Opinion
26
therefore, that the total amount due for purposes of calculating reasonable attorney’s fees
included both the principal and interest, was not error.
C. Per Diem Interest
In its cross-appeal, MRA contends that the “circuit court mistakenly calculated the
fee award for Counts II and III based on the lower per diem interest attributable to Count
I.” We agree that the court appears to have made a clerical error in its calculations.
On December 4, 2020, the circuit court granted MRA’s application for an award of
reasonable attorney’s fees. In its order, the court calculated attorney’s fees at a rate of 30
percent of the judgment amount plus pre- and post-judgment interest. The court then
calculated the per diem interest rates applicable to each of the three counts of the Second
Amended Complaint. Because it appears that court erroneously applied the per diem
interest rate for Count I (Contract .02) to its calculation of per diem interest on the
judgments for Count II (Contract .03) and Count III (Contract .04), we will remand the
case to the circuit court to enter a revised order correcting the calculation of the per diem
interest to be entered as to Counts II and III.
JUDGMENT OF THE CIRCUIT COURT
FOR HOWARD COUNTY AFFIRMED.
CASE REMANDED FOR FURTHER
PROCEEDINGS CONSISTENT WITH
THIS OPINION. COSTS TO BE PAID BY
APPELLANTS.