Victoria Government Gazette S 98 23 May 2003 3
(e) the builder warrants that if the work consists of the erection or
construction of a home, or is work intended to renovate, alter, extend,
improve or repair a home to a stage suitable for occupation, the home will
be suitable for occupation at the time the work is completed;
(f) if the contract states the particular purpose for which the work is required,
or the result which the building owner wishes the work to achieve, so as
to show that the building owner relies on the builder's skill and judgment,
the builder warrants that the work and any material used in carrying out
the work will be reasonably fit for that purpose or will be of such a nature
and quality that they might reasonably be expected to achieve that result.
10. Policy to state that indemnity extends to acts or omissions of others
The policy must state that the indemnities referred to in clauses 8 and 9 include an
indemnity in respect of the acts or omissions of all persons who were contracted by the
builder to perform the domestic building work under the insurable domestic building
contract resulting in loss or damage of the kind referred to in clause 8 or 9.
11. To whom does the cover extend?
The required insurance cover in the policy must extendÑ
(a) to each person who becomes entitled to the benefit of any of the warranties
referred to in clause 8(2)(b); and
(b) to the owner for the time being of the building or land in respect of which the
domestic building work is or was being carried out.
12. Period of insurance
(1) The policy must provide the indemnities referred to in clauses 8 and 9 in relation
to non-structural defects in respect of loss or damage occurring during the period
commencing on the commencement day and ending not earlier than 2 years after
the earlier ofÑ
(a) the completion date of the domestic building work; and
(b) the date of termination of the relevant domestic building contract.
(2) The policy must provide the indemnities referred to in clauses 8 and 9 in respect
of all other loss or damage occurring during the period commencing on the
commencement day and ending not earlier than 6 years after the earlier ofÑ
(a) the completion date of the domestic building work; and
(b) the date of termination of the relevant domestic building contract.
13. Penalties for delay by builder
(1) The policy may exclude or limit claims under the policy for penalties, fines,
liquidated damages or other sums, if any of these relate to delay on the part of the
builder.
(2) Despite sub-clause (1), the policy must not exclude or limit any increase in
rectification costs caused by the effluxion of time.
14. Excessive payments to builder
The policy may exclude or limit claims under the policy for money paid to a builder that
exceeds the amounts that should have been paid to the builder in accordance with section
11 and (as the case requires) section 40(2) or section 40(3) or section 40(4) of the Domestic
Building Contracts Act 1995.
15. Builder dies, disappears etc. before work begins
(1) The policy may exclude or limit claims under the policy for non-completion of
building work if the death, insolvency or disappearance of the builder occurs
before the builder commences on the building site any domestic building work