Yes
N/A
q. Indicate design dead and live, wind, snow, seismic loads for oor areas, roofs,
balconies, porches, breezeways, corridors, stairs, mezzanines and platforms.
Show concentrated loads, i.e. le rooms, machinery and forklift areas, if greater
than those shown on the Code Summary Sheet. Identify shear walls, bracing,
strapping fastening, reinforcement and any special anchoring required.
Yes
N/A
r. Where applicable, indicate on roof framing plan where concentrated loads
(mechanical equipment, cranes, etc.) will be placed.
Yes
N/A
s. Indicate on foundation and framing plans the location and lateral load resisting
system. (Show walls, braced frames, moment connections, etc.)
FIRE PROTECTION PLANS:
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
a. Complete a sprinkler design data sheet and include it on the rst plan of the
sprinkler drawings.
b. Show oor plans for each oor with sprinkler piping layout, pipe sizes, pipe
hanger details, piping materials, doors, walls and room identities.
Often, these shop drawings are not available at the time of initial plan
submission. If this is the case, write in “NA,” but note the following:
• These shop drawings must be submitted for department review and
approval at least two weeks before the projected installation date.
• Failure to obtain approval of these drawings before installation could result
not only in delay of the nal inspection and issuance of an occupancy
permit, but also in removal and reconstruction of installations which fail to
meet UCC requirements.
c. Show ceiling plans with sprinkler head(s) layout, walls, softs, openings, doors,
dimensions and room identities.
d. Verify system design by providing hydraulic calculations along with the
following:
Recent water ow test
Percent safety margin
Type of backow-preventer or reduced pressure zone showing equivalent
foot loss
Fire pump summary
e. Note the type of sprinkler system used (e.g., 13, 13D, or 13R)
f. For residential occupancies such as apartments and condominiums, show
sprinkler head locations at breezeways, if applicable.
g. Indicate the certied testing laboratory agency (e.g., U.L.), their test number
and hourly ratings of all new and/or affected rated members and assemblies
(i.e. columns, beams, oor/ceiling and ceiling/roof re-rated design assemblies).
Show all new and/or affected re-rated walls with their ratings, if not shown
elsewhere.
h. All penetrations of re-rated construction must be per manufacturer’s details.
Details shall meet or exceed ratings of construction being penetrated. The
penetration details shall be exactly as tested by a certied testing laboratory or
agency and shall include their system numbers. All new penetrations of existing
re-rated walls and assemblies shall be shown with appropriate designs.
i. Provide a re alarm riser showing connection to a UL-approved central station.
Show tamper switches on both OS and Y valves of backow prevention device,
unless shown elsewhere.
j. Indicate commodity class (per section 2303 of the International Fire Code) and
height of any storage.
k. Provide Material Safety Data Sheets for any hazardous materials (also specied
under “ARCHITECTURAL PLANS”).
UCC-2 REV 03-16 (Page 4)