NSW Auditor-General's Report
NSW Solar Bonus Scheme
KEY FINDINGS
2.3.1 Review of models underpinning the different projected costs of the
Scheme
UNSW reviewed the models that were used to forecast the different projected costs of the
Scheme over its life. Overall, I consider these models to be satisfactory. Comments on the
individual models follow (Refer Appendix 5 (a) for complete table and Appendices 5 (b) to (d)
for comment on each DNSP’s model):
Report Model UNSW Consultant comments
a
NSW
Feed-in
taskforce
(2009)
Estimated the Scheme costs for different
tariff settings given two assumed
scenarios of deployment as part of
scheme design.
A particularly challenging modelling task at
the early stages of Scheme design. PV
deployment not modelled as such, instead
assumed. PV generation appears to have
been estimated in house.
b
AECOM
Advice
(2009)
Estimated future deployment and the
Scheme costs for two tariff options as part
of Scheme design.
Review of this modelling limited and based
on discussions with stakeholders that were
intended to better understand the AECOM
(2010) modelling. PV uptake model was
an earlier version of AECOM (2010) model
and incorporated 2009 PV system price
estimates. PV performance model
apparently the same as AECOM (2010),
as was eligible generation estimate.
c & d
(2010)
Estimated future deployment and the
Scheme costs given early experience with
scheme and 50 MW review trigger.
Scenarios of possible tariff changes
investigated.
Estimated Scheme costs of $2.7 billion
(60 cents gross, seven years).
PV deployment model based on modified
NPV function using statistical tariff from
historical Australian PV uptake.
Incorporated much lower installed PV
system costs than earlier models given
2010 data. PV performance model
provided by AECOM in-house research
group.
e& f
DNSP#1
(ongoing)
Two separate budget impacts models:
one used for input to Parry Duffy and one
used for ongoing reporting to DTIRIS.
In-house budgeting models based on
system application and connection data.
PV performance based on DNSP#1’s
consultant advice. Ongoing model
development
and tuning given the Scheme
closure and system application and
connection data.
e & f
DNSP#2
(ongoing)
Three separate budget impacts models:
one used for input to Parry Duffy, one
used for ongoing reporting to DTIRIS and
one provided as including the latest data.
In-house budgeting models based on
system application and connection data.
PV generation based on Clean Energy
Council data. Ongoing model development
and tuning given the Scheme closure and
system application and connection data
e & f
(ongoing)
A budget impacts model provided by
Oakley Greenwood, that includes some
scope for modelling deployment.
Model used for projecting deployment and
internal budgeting and AER pass through
request. PV generation based on ORER
performance estimates. Ongoing model
development and tuning given the Scheme
closure and system installation and
connection data.
f
Combined
DNSPs’
(ongoing)
Estimated budget impacts spreadsheet
consists of three main components.
June 2011 spreadsheet suggests total
the Scheme tariff costs of $1.75 billion.
Component 1 sums ongoing DNSP
reporting of estimated tariff costs.
Component 2 summarises the Scheme
applications and connections with respect
to net and gross 60 cents and 20 cents
Scheme participants.
Component 3 presents various scenarios
based on former Scheme options.
Reviewed by DNSPs’ consultant.