Contracts for state and local public construction projects
typically contain clauses stating how contractors may
recover compensation for increased costs due to changes
or additions to the scope of work. Such clauses may
include written change order, notice, and approval
requirements, and unit prices for increased material quan-
tities. They also may limit the contractor’s recovery for
change impacts by setting fixed overhead recovery per-
centages, by restricting total value to a capped amount
(e.g., the contract price), or by stating that certain impacts
are not recoverable.
But what happens when the number or scope of
changes on a public project are excessive, such that they
go beyond what either party anticipated at contracting? In
those circumstances, contract clauses may be inadequate
to compensate the contractor because the impacts of those
changes exceed what the contractor included in its con-
tract price or can add onto the contract under contract
procedures. Unless the contractor is allowed to go beyond
the contract for a remedy, it will be faced with the difficult
decision of whether to incur costs it cannot recover or
walk off the job and risk a default termination. In many
jurisdictions, contractors need not face such a decision
because they can recover under the doctrines of abandon-
ment and cardinal change.
The doctrines of abandonment and cardinal change
provide that a contractor may recover its increased costs
in quantum meruit where they result from excessive,
o w n e r-directed changes to a project, beyond what the par-
ties could have reasonably anticipated at contracting.
Contract provisions concerning change procedures and
pricing do not apply to a claim for these costs. Under
these circumstances, the owner is said to have “aban-
doned” the contract or made a “cardinal change” to the
contract. Different jurisdictions use different terminology
(although, as discussed below, at least one jurisdiction,
California, treats the doctrines differently).
This article discusses the different state laws affecting
recovery under the doctrines of abandonment and cardi-
nal change on public projects. As will be apparent, a
s t a t e ’s law is not always clear.
Many Jurisdictions Recognize Abandonment or
Cardinal Change Generally
The abandonment and cardinal change doctrines are
widely accepted. Courts applying federal contract law
have recognized the cardinal change doctrine since the
1 9 6 0 s .
1
For private construction projects, some form of
abandonment or cardinal change doctrine has been
expressly recognized under the laws of at least 23 states
and Puerto Rico,
2
and the doctrine has been implicitly
recognized by at least four other states and the District of
C o l u m b i a .
3
It is unclear in many of those jurisdictions,
h o w e v e r, whether the courts would apply the doctrine to
public projects. In one jurisdiction, California, the state
supreme court has explicitly ruled that abandonment,
while available for private projects, is n o t available for
public projects.
4
Whether abandonment and cardinal change claims are
viable on any type of project remains an open question in
all but one of the remaining 23 states. The exception is
Mississippi, which has expressly rejected the abandonment
and cardinal change doctrines for all projects.
5
Abandonment versus Cardinal Change
Most jurisdictions that recognize the abandonment and
cardinal change doctrines make no distinction between
the two doctrines. In those jurisdictions, either or both
doctrines allow for contractor claims for added costs
caused by excessive changes beyond the general scope of
work of the contract. For example, in L.K. Comstock &
Co., Inc. v. Becon Constr. Co., Inc.,
6
which involved a
private construction project, the Eastern District of
Kentucky discussed the two theories separately, but noted
that both doctrines address “situations where ordered
changes exceed the general scope of the contract” and
that “[r]egardless of which theory is applied, the result is
the same: the party performing the work is entitled to
seek a remedy outside the contract for the reasonable
value of work performed.
7
In the case before it, the dis-
trict court found that the changes ordered were within
the parties’ expectations at contracting and so rejected
the contractors’ claim under both the abandonment and
cardinal change theories.
8
California is the exception. In Amelco Electric v. City
of Thousand Oaks, the California Supreme Court distin-
guished the doctrines, calling them “fundamentally differ-
e n t . ”
9
According to the court, under an abandonment
claim, the contractor is entitled to recover its total cost
(less payments received) for work both before and after
the contract was abandoned. In contrast, under a cardinal
change claim, the contractor is only entitled to breach of
contract damages for the additional work constituting a
cardinal change. While the court rejected a public con-
t r a c t o r ’s right to bring an abandonment claim, it purport-
ed not to address a contractor’s right to bring a cardinal
change claim.
1 0
Abandonment and Cardinal Change on State
and Local Construction Pro j e c t s
A
A R O N
P. S
I L B E R M A N
Aaron P. Silberman is a shareholder at Rogers Joseph O’Donnell &
Phillips in San Francisco, California.
Number 3 • Volume 39 • Spring 2004 • American Bar Association • The Procurement Lawyer • 17
“Abandonment & Cardinal Change on State & Local Construction” by Aaron P. Silberman, published in The Procurement Lawyer, Volume 9, No.3,
Spring 2004 © 2004 by the American Bar Association. Reproduced by permission. All rights reserved. This information or any portion thereof may not be
copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the
American Bar Association.
prclawSPR04 6/21/04 5:12 PM Page 17
substantial changes to the project while giving Amelco no
extra time to complete the additional work.”
1 6
As a result,
the City issued more than 1,000 sketches to clarify or
change the original contract drawings, nearly a quarter of
which affected the electrical cost. The City agreed to only
31 of Amelco’s 221 requested change orders, increasing
the contract price by $1 million. At the end of the project,
Amelco filed a claim against the City that eventually
totaled more than $2 million for the additional uncom-
pensated work, based on a theory that the City abandoned
the original contract through its excessive change orders.
The City denied Amelcos claim.
Amelco sued the City under an abandonment theory
of liability. Under that theory, existing California case law
held that a contractor could recover from a private owner
for the reasonable value of its services where the owner
had made so many changes to a contract that it could be
deemed to have abandoned the contract.
1 7
At trial, the
court allowed Amelco to submit evidence of its damages
under an abandonment theory, and Amelco prevailed.
After the court of appeal affirmed, the City appealed to
the California Supreme Court.
The California Supreme Court reversed the court of
a p p e a l ’s decision, holding that a contractor cannot recov-
er against a public owner under the theory of abandon-
ment. The court relied on California’s void contract rule
that prohibits a contractor from being paid for work per-
formed under a contract that is subsequently declared
void because the public owner was not authorized to
award the contract in the first place.
1 8
In A m e l c o, the
court extended the application of this rule from problems
that arise during the bidding of a contract to problems
that arise during performance. The court concluded that
allowing abandonment claims in the public works con-
text would render the concept of competitive bidding
m e a n i n g l e s s .
1 9
Although the court did not reach the issue of whether
a cardinal change claim would be viable on public projects
in California, it is unclear under the court’s logic how
contractors could assert cardinal change claims against
public owners when they cannot bring abandonment
claims against such owners.
2 0
In their dissent, two justices noted that most jurisdic-
tions allow abandonment claims and that, under the
majority decision, California becomes the first jurisdic-
tion to allow abandonment claims for private but not
public projects.
2 1
The dissent opined that allowing aban-
donment claims for public projects would benefit the
public because it would deter poor construction planning
and management by public entities and because disallow-
ing such claims would lead contractors to stop building
where the public owner had imposed excessive changes,
rather than continuing to work at the risk of never get-
ting paid.
2 2
More recently, a California court of appeal has inter-
preted the rule in A m e l c o as applying only to contractor
claims made directly to public owners.
2 3
In S e h u l s t e r
D i ff e rent Jurisdictions’ Approaches to Abandonment
and Cardinal Change
Mississippi does not allow contractors to recover for
abandonment or cardinal change on any type of project.
According to a federal district court (the only court to
opine on the issue), Mississippi law does not allow public
or private contractors to recover under an abandonment
or cardinal change theory. The seminal case is L i t t o n
Systems, Inc. v. Frigitemp Corp., which involved a dispute
between the prime contractor and one of its subcontrac-
tors on a federal project.
1 1
In that case, Litton had hired
Frigitemp as a subcontractor for its construction of
Landing Helicopter Assault vessels for the United States.
After Litton sued Frigitemp for backcharges, Frigitemp
countersued on several grounds, including cardinal
change, seeking recovery for extra work in quantum
meruit. The district court granted Litton’s motion for
summary judgment on Frigitemp’s cardinal change claim,
holding that such claims are not recognized under
Mississippi law.
1 2
In Litton Systems, Frigitemp had submitted evidence
that “large scale changes were made to the contract work
during the course of construction” and expert testimony
that those changes “were so massive that no one could
have anticipated them at the time of contracting.
1 3
Frigitemp relied on cardinal change cases, primarily from
the U.S. Court of Claims, none of which applied
Mississippi law. The district court refused to follow those
cases, relying instead on Mississippi court decisions stating
that, in order to recover under quantum meruit, a party
must show (1) that it performed work that was not antici-
pated by the contract and (2) that there were no provi-
sions in the contract concerning payment for unanticipat-
ed extra work. Since Frigitemp could not prove the latter
element, its claim failed as a matter of law.
1 4
California allows prime contractors to recover for
abandonment only on private jobs, but allows subcon-
tractors to recover from prime contractors both on pri-
vate and public jobs. In Amelco Electric v. City of
Thousand Oaks,
1 5
California became the first jurisdiction
to make a distinction between private and public projects
with regard to abandonment claims, allowing prime con-
tractors to recover on such claims only for private jobs.
The California Supreme Court held in A m e l c o that a
contractor cannot rely on the abandonment theory of lia-
bility to recover its added costs from a public owner
where the owner made excessive changes beyond the ini-
tial scope of the contractor’s work.
The facts in A m e l c o provide a textbook case for an
abandonment claim. A m e l c o arose from a contract to pro-
vide electrical work as part of the construction of a civic
arts plaza. The City of Thousand Oaks awarded Amelco
the contract after Amelco presented the low bid of $6.1
million. As the dissenting opinion noted, “It appears the
City let the project out for bid before its plans were suffi-
ciently complete . . ., and then imposed numerous and
Number 3 • Volume 39 • Spring 2004 • American Bar Association • The Procurement Lawyer • 18
“Abandonment & Cardinal Change on State & Local Construction” by Aaron P. Silberman, published in The Procurement Lawyer, Volume 9, No.3,
Spring 2004 © 2004 by the American Bar Association. Reproduced by permission. All rights reserved. This information or any portion thereof may not be
copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the
American Bar Association.
prclawSPR04 6/21/04 5:12 PM Page 18
Tu n n e l s / P r e - C o n v. Traylor Bros. Inc./Obayashi Corp., the
court held that A m e l c o does not preclude a subcontractor
on a public project from recovering from the prime con-
tractor under an abandonment theory.
In S e h u l s t e r, Traylor Brothers contracted with the City
of San Diego to build a tunnel and subcontracted with
Sehulster for the manufacture and supply of tunnel ring
segments. After Traylor Brothers made substantial
changes to its purchase order, Sehulster submitted a claim
for cost overruns it attributed to the changes. When
Traylor Brothers rejected the claim, Sehulster sued for
breach of contract and abandonment, and Tr a y l o r
Brothers cross-complained against the city for indemnity.
The jury awarded Sehulster $2.8 million in damages and
determined that Traylor Brothers was entitled to 30 per-
cent indemnity from the city.
The court of appeal affirmed the abandonment award,
but reversed the indemnity determination. It
found that “the public policy considerations
underlying the Supreme Court’s decision [in
A m e l c o] do not apply in the context of two con-
tracting private entities.”
2 4
Since the court also
found that Traylor Brothers was not entitled to
implied contractual indemnity under the partic-
ular facts of the case, it declined to consider
whether Amelco would preclude a contractor
from recovering from the public owner under an implied
contractual indemnity theory where it has incurred liabil-
ity under an abandonment theory.
2 5
Eight states and Puerto Rico expressly or implicitly
allow contractors to recover for abandonment on public
j o b s . In contrast to California and Mississippi, at least
eight other states (Arizona, Arkansas, Illinois, Maine, New
York, Oregon, Washington, and Wyoming) and Puerto
Rico have allowed abandonment claims against public
o w n e r s .
2 6
All of those jurisdictions, except Maine and
Wyoming, have expressly allowed such claims. A court in
Wyoming has simply assumed the doctrine applies to pub-
lic contracts, asking instead whether it should also apply to
private jobs.
2 7
And the Supreme Judicial Court in Maine
implicitly recognized the cardinal change doctrine in a
public contract case, although it declined to apply the doc-
trine on the facts before it.
2 8
An Arkansas decision, Housing Authority of Te x a r k a n a
v. E.W. Johnson Constr. Co.,
2 9
is typical of courts’ applica-
tion of the abandonment theory to public contracts.
There, a city had directed numerous changes,
3 0
which the
trial court found constituted a breach of contract in find-
ing for the contractor.
3 1
On appeal, the city argued “that
the contract permits the owner to make changes in the
work of the contractor without invalidating the con-
t r a c t . ”
3 2
The Arkansas Supreme Court was unpersuaded
and affirmed the trial court holding that the city
“breached the warranty of the plans and specifications
submitted to the [contractor] resulting in cardinal
changes in the contract.”
3 3
Another example of a court applying the abandon-
ment doctrine to a public project is the Arizona court’s
decision in County of Greenlee v. We b s t e r .
3 4
In that case,
the plaintiff contracted with the County of Greenlee to
construct and improve a roadway. During construction,
the county made many alterations in its plans and specifi-
cations, resulting in alteration of the quantity, location,
and extent of the work. The contractor sued for breach of
contract, contending that the county’s alterations were
unreasonable and changed the general character of the
contract. After the trial court denied the county’s request
for dismissal, the county appealed. Citing Cook County v.
H a r m s, an abandonment case involving a public project
in Illinois,
3 5
the court stated that changes clauses general-
ly cover “only such alterations as are incident to and in
aid of the main contract,” and do not cover “[c]hanges
that radically extend the amount of the work, or that
eliminate large portions of the work, or that greatly
increase the cost thereof.
3 6
On this basis, the court con-
cluded the contractor was not entitled to recover under
the contract, but was entitled to recover in quantum
meruit. Since the contractor had not pled a quantum
meruit claim, the appellate court directed the trial court
to dismiss the contractor’s breach of contract complaint.
Eighteen other states and Washington, D.C., allow
contractors to recover for abandonment on private jobs,
but whether they would allow recovery on public jobs
has not been decided. Many other states have adopted
the abandonment doctrine or something similar for pri-
vate contracts, but have not addressed the doctrine’s
applicability to public jobs, at least not in any reported
decisions. States that have expressly recognized abandon-
ment or cardinal change on private projects, but have not
addressed public projects, include Alabama, Colorado,
Indiana, Kentucky, Louisiana, Maryland, Michigan,
Minnesota, Missouri, Nevada, Ohio, South Dakota,
Texas, Utah, and Wi s c o n s i n .
3 7
Three more states
Oklahoma, Pennsylvania and Rhode Island—and
Washington, D.C., have also implicitly recognized aban-
donment or cardinal change, but have only done so in
the context of private jobs.
3 8
No reported case has decid-
ed whether any of these jurisdictions would allow recov-
ery under either theory on public jobs.
At least one jurisdiction, Michigan, has limited appli-
cation of the abandonment doctrine in a way that would
likely preclude abandonment recovery on public jobs.
S p e c i f i c a l l y, in R.M. Ta y l o r, Inc. v. General Motors Corp.,
the Eighth Circuit held that abandonment claims are not
allowed under Michigan law where the parties’ contract
Many states have adopted the abandonment
doctrine for private contracts, but have not
a d d r essed the doctrine’s applicability to public jobs.
Number 3 • Volume 39 • Spring 2004 • American Bar Association • The Procurement Lawyer • 19
“Abandonment & Cardinal Change on State & Local Construction” by Aaron P. Silberman, published in The Procurement Lawyer, Volume 9, No.3,
Spring 2004 © 2004 by the American Bar Association. Reproduced by permission. All rights reserved. This information or any portion thereof may not be
copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the
American Bar Association.
prclawSPR04 6/21/04 5:12 PM Page 19
contains a change order clause.
3 9
Since such clauses are
c o m m o n l y, if not always, used in public contracts, this
limitation effectively eliminates abandonment claims on
such projects in Michigan. Unlike Michigan, most juris-
dictions that allow abandonment claims have not
imposed this limitation.
4 0
Other than Michigan and, of course, California, most
jurisdictions that have recognized abandonment for pri-
vate projects would likely recognize the doctrine for pub-
lic projects as well. California’s refusal to allow abandon-
ment claims on public jobs depends on its “void contract
r u l e , ”
4 1
which is not the law in most states. Without that
rule, California’s rationale for distinguishing between pri-
vate and public jobs for purposes of allowing contractor
recovery would not apply.
The remaining 22 states have neither recognized nor
rejected recovery for abandonment. The courts in 22
states have not yet considered abandonment or cardinal
change in any reported decision. In most, if not all, of
these jurisdictions, contractors could assert claims under
either theory based on basic contract and waiver princi-
ples. The courts in these jurisdictions would likely follow
the majority rule and allow recovery on private and pub-
lic jobs, unless they have a void contract rule similar to
that in California.
Conclusion
When projects go bad, contractors need to look at the
possibility of asserting abandonment or cardinal change
claims. In some jurisdictions, such claims have been
explicitly recognized for public projects. Many other juris-
dictions have recognized either or both theories in the
context of private jobs, but have not addressed whether
they would allow recovery for public jobs. In still others,
the door is open under the right facts to assert an aban-
donment or cardinal change claim under basic contract
and waiver principles. For public projects in California
and all projects in Mississippi, however, that door has been
shut. Whether other jurisdictions choose to follow Cali-
fornia or Mississippi in this regard remains to be seen.
PL
Endnotes
1. See, e.g., In re Boston Shipyard Corp., 886 F.2d 451, 456 (1st
Cir. 1989); Edward R. Marden Corp. v. United States, 442 F.2d
364, 369 (Ct. Cl. 1971); Air-A-Plane Corp. v. United States, 408
F.2d 1030, 1033 (Ct. Cl. 1969).
2. A l a b a m a : Hutchinson v. Cullum, 23 Ala. 622 (1853);
A r i z o n a : County of Greenlee v. Webster, 25 Ariz. 183 (1923);
A r k a n s a s : Hous. Auth. of Texarkana v. E. W. Johnson Constr.
Co., 264 Ark. 523 (1978); C a l i f o r n i a : C. Norman Peterson Co. v.
Container Corp. of Am., 172 Cal. App. 3d 628 (1985); C o l o r a d o :
H.T.C. Corp. v. Olds, 486 P.2d 463, 466 (Colo. App. 1971);
I l l i n o i s : Cook County v. Harms, 108 Ill. 151 (1883); I n d i a n a :
Rudd v. Anderson, 285 N.E.2d 836 (Ind. App. 1972); K e n t u c k y :
L.K. Comstock & Co. v. Becon Constr. Co., 932 F. Supp. 906, 933
(E.D. Ky. 1993) (applying Kentucky law); L o u i s i a n a : Nat Harrison
Assoc., Inc. v. Gulf States Utilities Co., 491 F.2d 578, 583, r e h ’ g
d e n i e d , 493 F.2d 1405 (5th Cir. 1974) (applying Louisiana law);
M a r y l a n d : Westinghouse Elec. Corp. v. Garrett Corp., 437 F.
Supp. 1301, 1332 (D. Md. 1977) (applying Maryland law);
M i c h i g a n : R. M. Taylor, Inc. v. General Motors Corp. 187 F.3d
809 (8th Cir. 1999), cert. denied, 528 U.S. 1159 (2000) (applying
Michigan law); M i n n e s o t a : Fuller Co. v. Brown Minneapolis Tank
& Fabricating Co., 678 F. Supp. 506, 509 (E.D. Pa. 1987) (applying
Minnesota law); M i s s o u r i : Baerveldt & Honig Constr. Co. v. Dye
Candy Co., 212 S.W.2d 65, 69 (Mo. 1948); Havens Steel Co. v.
Randolph Eng’g Co., 613 F. Supp. 514, 533 (W.D. Mo. 1985);
N e v a d a : Paterson v. Condos, 55 Nev. 134 (1934); New York:
Kole v. Brown, 13 A.D.2d 920 (1961); O h i o : Oberer Constr. Co.
v. Park Plaza, Inc., 179 N.E.2d 168, 171 (Oh. Ct. App. 1961);
O r e g o n : Hayden v. Astoria, 74 Or. 525, 533 (1915); Puerto Rico:
Paul N. Howard Co. v. Puerto Rico Aqueduct & Sewer Auth., No.
80–0743(RA), slip op. (D.P.R. 8/23/83) at 37b, a f f ’ d, 744 F.2d 880
(1st Cir. 1984), cert. denied, 469 U.S. 1191 (1985); South Dakota:
Peter Kiewit Sons’ Co. v. Summit Constr. Co., 422 F.2d 242,
254–55 (8th Cir. 1969) (applying South Dakota law); T e x a s : N a t ’ l
Envtl. Service Co., Inc. v. Homeplace Homes, Inc., 961 S.W.2d
632, 635 (Tex. App. 1998); U t a h : Rhodes v. Clute, 53 P. 990 (Ut.
1898); W a s h i n g t o n : Kieburtz v. City of Seattle, 84 Wash. 196
(1915); W i s c o n s i n : Olbert v. Ede, 156 N.W.2d 422 (Wis. 1968);
and W y o m i n g : Scherer Constr., LLC v. Hedquist Constr., Inc., 18
P.3d 645, 656 (Wyo. 2001).
3. District of Columbia: Blake Constr. Co., Inc. v. C. J.
Coakley Co., Inc., 431 A.2d 569, 578–79 (D.C. Ct. App. 1981);
M a i n e : Claude Dubois Excavating v. Kittery, 634 A.2d 1299,
1301–02 (Me. 1993); O k l a h o m a : Watt Plumbing, Air
Conditioning & Elec., Inc. v. Tulsa Rig, Reel & Mfg. Co., 533 P.2d
980 (Okla. 1975) (rejecting subcontractor’s claim, and distinguish-
ing cardinal change cases, based on express agreements between
subcontractor and contractor regarding compensation for each
change before altered work was performed); P e n n s y l v a n i a : E . C .
Ernst, Inc. v. Koppers Co., Inc., 476 F. Supp. 729, 757–58 (W.D.
Pa. 1979); Rhode Island: Clark-Fitzpatrick, Inc./Franki Found. Co.
v. Gill, 652 A.2d 440, 442 (R.I. 1994) (judgment below awarded
contractor damages for cardinal change claim).
4. 27 Cal. 4th 228 (2002). The California Supreme Court
denied Amelco’s application for rehearing on March 13, 2002.
Amelco Elec. v. City of Thousand Oaks, 2002 Cal. LEXIS 1689
( 3 / 1 3 / 0 2 ) .
5. Litton Sys., Inc. v. Frigitemp Corp., 613 F. Supp. 1377 (S.D.
Miss. 1985) (applying Mississippi law) (citing Jackson v. Sam
Finley, 366 F.2d 148 (5th Cir. 1966)); Citizens Nat’l Bank v. L.L.
Glascock, Inc., 243 So. 2d 67 (Miss. 1971); Delta Constr. Co. v.
City of Jackson, 198 So. 2d 592 (Miss. 1967); and Redd v. L&A
Contracting Co., 151 So. 2d 205 (Miss. 1963)). In L i t t o n, the
District Court quotes R e d d, 151 So. 2d at 208, stating that “where
there is a contract, parties may not abandon same and resort to
quantum meruit.” 613 F. Supp. at 1382. The court then concludes
that “Mississippi does not subscribe to the cardinal change doc-
trine.” I d . at 1384.
6. 932 F. Supp. 906 (E.D. Ky. 1993).
7. Id. at 939.
8. I d . at 935–36, 946; see also Scheck Mech. Corp. v. Borden,
Inc., 186 F. Supp. 2d 724, 734–35 (W.D. Ky. 2001).
9. 27 Cal. 4th 228, 238 (2002).
10. 27 Cal. 4th 228, 238 (2002).
11. See supra note 5.
12. I d. at 1382–84 (citing Jackson v. Sam Finley, 366 F.2d 148
(5th Cir. 1966)) (Mississippi does not subscribe to the cardinal
change doctrine. . . .”).
13. I d . at 1381.
14. I d . at 1382 (citing Citizens Nat’l Bank v. L.L. Glascock, Inc.,
243 So. 2d 67 (Miss. 1971); Delta Constr. Co. v. City of Jackson,
198 So. 2d 592 (Miss. 1967); Redd v. L&A Contracting Co., 151
So. 2d 205 (1963)).
15. 27 Cal. 4th 228 (2002).
16. A m e l c o, 27 Cal. 4th at 251-52 (J. Werdegar, dissenting).
Number 3 • Volume 39 • Spring 2004 • American Bar Association • The Procurement Lawyer • 20
“Abandonment & Cardinal Change on State & Local Construction” by Aaron P. Silberman, published in The Procurement Lawyer, Volume 9, No.3,
Spring 2004 © 2004 by the American Bar Association. Reproduced by permission. All rights reserved. This information or any portion thereof may not be
copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the
American Bar Association.
prclawSPR04 6/21/04 5:12 PM Page 20
Co., No. 80–0743(RA), slip op. (D.P.R. 8/23/83) at 37b, a f f ’ d, 744
F.2d 880 (1st Cir. 1984), cert. denied, 469 U.S. 1191 (1985); see also
Stuart A. Weinstein-Bacal, Construction in Puerto Rico: Navigating
the Legal Quagmire, 71 R
E V
. J
U R
. U. P.R. 29 (2002).
27. Scherer Constr., LLC v. Hedquist Constr., Inc., 18 P.3d 645,
656 (Wyo. 2001).
28. Claude Dubois Excavating v. Kittery, 634 A.2d 1299,
1301–02 (Me. 1993).
29. 264 Ark. 523 (1978).
30. I d . at 528 n.2.
31. I d . at 532–33.
32. I d . at 533.
33. I d . at 525, 529, 535.
34. 25 Ariz. 183.
35. 108 Ill. 151.
36. 25 Ariz. at 191–92.
37. S e e s u p r a note 2.
38. S e e s u p r a note 3.
39. 187 F.3d 809, 81314 (8th Cir. 1999) (applying Michigan law).
40. See, e.g., Peter Kiewit Sons’, 422 F.2d 242, 254-55 (8th Cir.
1969) (applying South Dakota law) and Bogert Constr. Co. v.
Lakebrink, 404 S.W.2d 779, 782 (Mo. Ct. App. 1966) (both cited
by R.M. Taylor, 187 F.3d at 813–14).
41. A m e l c o, 27 Cal. 4th at 238.
17. I d . at 235–36 (majority opin., citing C. Norman Peterson Co.
v. Container Corp. of Am., 172 Cal. App. 3d 628 (1985);
Daugherty Co. v. Kimberly-Clark Corp., 14 Cal. App. 3d 151
(1971); Opdyke & Butler v. Silver, 111 Cal. App. 2d 912 (1952)).
18. I d . at 238 (citing Miller v. McKinnon, 20 Cal. 2d 83, 87–88
(1942); Zottman v. City and County of San Francisco, 20 Cal. 96,
99–102 (1862)).
19. I d . at 238–39.
20. 27 Cal. 4th at 238.
21. I d . at 248–49 (J. Werdegar, dissenting).
22. I d . at 252–53.
23. Sehulster Tunnels/Pre-Con v. Traylor Bros. Inc./Obayashi
Corp., 111 Cal. App. 4th 1328, 1343–45 (2003).
24. I d . at 1344–45.
25. I d . at 1352 n.22.
26. County of Greenlee v. Webster, 25 Ariz. 183 (1923); Hous.
Auth. of Texarkana v. E. W. Johnson Constr. Co., 264 Ark. 523
(1978); Cook County v. Harms, 108 Ill. 151 (1883); Claude
Dubois Excavating v. Kittery, 634 A.2d 1299, 1301–02 (Me.
1993); Westcott v. State, 36 N.Y.S.2d 23 (1942); Hayden v.
Astoria, 74 Or. 525 (1915); Kieburtz v. City of Seattle, 84 Wash.
196 (1915); Scherer Constr., LLC v. Hedquist Constr., Inc., 18
P.3d 645, 656 (Wyo. 2001) (assumes, without deciding, that cardi-
nal change doctrine applies to public owners); Paul N. Howard
Number 3 • Volume 39 • Spring 2004 • American Bar Association • The Procurement Lawyer • 21
“Abandonment & Cardinal Change on State & Local Construction” by Aaron P. Silberman, published in The Procurement Lawyer, Volume 9, No.3,
Spring 2004 © 2004 by the American Bar Association. Reproduced by permission. All rights reserved. This information or any portion thereof may not be
copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the
American Bar Association.
prclawSPR04 6/21/04 5:12 PM Page 21