THE CONSTRUCTION LAWYER 5Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
BREACHES
OF CONTRACT
Dissecting Contract Breach
Terminology, Warranties,
and Remedies: Part Two
By Jerey P. Aiken and Dylan C. Ochoa
Editor’s note: This is part two
in a series of articles. Part one
was published in the last issue
of The Construction Lawyer.
Introduction
In part one of this article, we
discussed the various inconsis-
tencies and deciencies within
the prevailing nomenclature
associated with the classica-
tion of contractual breaches
and r
esulting remedies. The
focus was on three traditional
approaches: first, material
breach; second, partial vs. total
breach; and nally, a hybrid of
a total, partial, and material
breach. The chosen conceptual approach is critical to
determine the appropriate remedy, such as entitlement
to monetary damages, or avoidance of further perfor-
mance obligations. Therefore, part two of this series of
articles offers a proposed solution to the existing prob-
lems within the traditional approaches drawing from the
unique, process-oriented, practice of construction law.
Contract Breach in Construction—The Solution
Descriptive Nomenclature
Given the shortcomings of the three binary approaches to
contractual breach, it is unsurprising that they simply do
not work well when applied to process-oriented contracts
involving interdependencies between the contracting par-
ties, for example, as encountered in construction. It is for
this reason, among others, that the traditional approach to
construing contractual breach presents unique challenges
in the construction arena. We submit that constructions
three-tier approach of substantial breach, material breach,
and immaterial/technical breach more accurately reects
what one should encounter from an appropriately descrip-
tive, and logically-consistent, classication of contractual
breach.
1
For example, at the highest rung of recovery, a
substantial breach entitles one to exercise a termination
option in addition to recovering damages.
2
Such a breach
can only occur in the absence of substantial completion
of one’s performance (how one can substantially breach
a substantially performed contract is confusing at best).
3
Following substantial performance, the only breaches
are (a) a material breach, allowing the recovery of dam-
ages but subject to the limitation of economic waste and
diminished value; and (b) an immaterial/technical breach,
which does not provide for any monetary relief equal to
a material breach where the basis for an award would
result in economic waste without any diminution in value.
It would seem appropriate to start the process of
developing appropriately descriptive terminology in the
world of contractual breach with the simple concept that
a breach must at least be material to justify any award of
damages, or other relief. In other words, the term mate-
rial should not be at the uppermost rung of the ladder,
entitling termination, or excusing non-performance, by
the nonbreaching party. Instead, it should be one rung
lower. Moving it down to the area where monetary dam-
ages are available, but excuse of non-performance is not,
allows for a more logical classication enabling the high-
est rung to occupy a substantial breach.
4
In this way, a
substantial breach triggers the right to terminate while
also triggering the right associated with any material
breach to recover damages for costs to complete, or to
cure, subject to the duty to mitigate such damages
5
and
application of the economic waste and diminished value
doctrines. This approach avoids the inconsistency of hav-
ing to dene material breach as to allow for exercise of
two potential remedies (i.e., termination and/or dam-
ages), leaving a breach allowing for only one remedy (i.e.,
damages) relegated to the bin of being classied as an
immaterial breach—a problem avoided with the partial
breach concept.
It is worthwhile to note that in the construction eld,
the term substantial is used to characterize a breach
entitling the other party to terminate.
6
Courts have
also employed this term in non-construction settings,
7
although doing so has been almost always without expla-
nation for abandoning the term material to characterize
the breach. Oftentimes, courts use the two terms syn-
onymously,
8
which only leads to confusion as to what is
really intended.
A breach should be considered substantial only if
substantial performance is not achieved. In this way,
there would be a common concept of what is, or is not,
Jerey P. Aiken
Dylan C. Ochoa
THE CONSTRUCTION LAWYER6 Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
substantial governing both the stage of performance
and the character of the breach. Some courts have done
so.
9
As a practical matter, equating total and substan-
tial for this category of breach makes much more sense.
In other words, once substantial performance has been
rendered, there can no longer be a substantial breach.
Again, the term substantial is applied with like meaning,
whereas material and total do not have a similar benet
in conveying equal concept terminology to both perfor-
mance and breach. A breach that results in less than a
destruction of the essence of the transaction, yet that is
signicant enough to be more than unimportant, should
be considered material to support an award of damages,
be it the cost to complete or repair, accrual of interest,
or diminished value. A breach that is truly unimportant
or inconsequential should be classied as a immaterial or
technical. Admittedly, any of these latter terms convey-
ing the concept of insignicance would depend upon an
inherent application of the economic waste and dimin-
ished value principles such that the diminished value, on
its face, would be zero.
Now, would this shift the burden of proof for the
breaching party seeking to avoid damages liability? No.
If, for example, the owner asserts a damages claim for
the cost to correct the construction of a stud wall to
move each stud one-quarter inch without any meaning-
ful improvement to the wall’s functionality, or structural
integrity, the contractor still has the burden of proving
the cure for the breach would entail economic waste and
would not produce an improvement in market value such
that it amounts to a purely technical or immaterial breach.
Again, the playground basketball adage of “no harm,
no foul” is particularly applicable to this type of breach.
Labeling it as an immaterial or technical breach would
be more descriptive, although in many cases a detailed
analysis of the cost to complete or correct in compari-
son to any diminishment in market value would still be
required to arrive at the same spot—namely, no recover-
able damages.
10
Remedies for Breach
It is hornbook law that absent a contractual provision
authorizing one party to make changes to the other’s
required performance (e.g., a “changes clause”), any
ordered change, or changes, amounts to a breach of con-
tract, or potentially, an abandonment. Whether such a
change amounts to a substantial, material, or technical/
immaterial breach is oftentimes a difcult question to
answer. Focus must be paid to whether the unauthorized
change involves the addition or deletion of work, plus its
relative signicance to the overall contractual arrange-
ment. The available remedies for a type of breach of this
nature will generally be determined under the same prin-
ciples as applicable to any other breach.
11
A rather unique aspect of construction law is the
treatment accorded to changes issued under a contrac-
tually-sanctioned changes clause and how, in certain
instances, that treatment exemplies aggregating multi-
ple material breaches to amount to a substantial breach,
thereby triggering a termination option under the First to
Breach rule. This happens via the concept of “death by a
thousand cuts, which has been recognized as a legitimate
vehicle for concluding that a series of less-than-substan-
tial changes by way of a changes clause, or otherwise, can
amount to a “cardinal change.”
12
Because, by denition,
a cardinal change entitles the contractor to either quit or
continue performance,
13
it is functionally equivalent to
substantial breach in terms of the remedies available. Yet,
no judicial decision specically equates the two. Neverthe-
less, this seems to provide fertile ground for establishing
that an aggregation, or series, of less-than-substantial
breaches can amount to a substantial breach triggering
the First to Breach option in areas outside the construc-
tion eld.
There is a related issue associated with monetary dam-
ages available under the cardinal change rule. While this
is a subject beyond the primary focus of this Article, suf-
ce it to say that the question becomes how a contractor
is entitled to be compensated should such a change occur.
Courts generally recognize the contractual scheme for
compensating a contractor under a changes clause does
not apply in the event of a cardinal change,
14
but instead
that the doctrine of quantum meruit applies.
15
The cen-
tral issue is the extent to which a contractor is entitled
to that measure of compensation. That is, is a contrac-
tor entitled to the reasonable value of the work which
was impacted by the cardinal change? Or is a contractor
entitled to the reasonable value of the work for the entire
project? If the latter, a contractor could salvage a project
that is underwater nancially and turn it into a protable
one. It might also avoid the need for acceleration at the
contractor’s ultimate expense if the contractor is behind
schedule up to the point of the cardinal change. If the
former, the contractor’s recovery would be limited to the
work impacted by the cardinal change, as has been held
in a case specically rejecting abandonment as a basis for
extending quantum meruit to pre–cardinal change work.
16
The general rule is that specic performance is not
available when the injured party can be adequately com-
pensated through an award of monetary damages, which
has been found specically applicable to construction
contracts.
17
Most often, this form of relief is relegated
to situations where something unique is the subject of
promised performance—such as in the case of contracts
involving the transfer of land, which is oftentimes deemed
unique by its nature.
18
Consequently, it is safe to conclude
that for an obligation to be subject to a specic perfor-
mance remedy, it must be of the essence of the transaction,
and its breach in turn would have to be substantial. In
short, a simple material breach would not be of such a
nature to qualify for this equitable remedy.
The recoverability of punitive damages is also worth
considering insofar as it relates to the three types of
breaches. Punitive damages obviously would not be
THE CONSTRUCTION LAWYER 7Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
available for a purely technical or immaterial breach
that does not even allow a monetary recovery, although a
theoretical exception would exist under a material-imma-
terial or total-partial construct. In these latter instances, a
minor breach that would not allow for recovery of mon-
etary damages due to application of the economic waste
and diminished value rules could still conceivably allow
for a punitive damages award, although it is difcult to
imagine such a situation.
19
That leaves recovery in the
event of a material or substantial breach. Generally, puni-
tive damages are not recoverable for contractual breach
because the law recognizes the concept of efcient breach,
which bars liability beyond making the nonbreaching
party whole.
20
If one is entitled to breach a contract inten-
tionally to accomplish an efcient breach, it stands to
reason that one is likewise free to breach it negligently or
otherwise. At least one court has failed to accept this logic
in upholding a punitive damages award when a written
seven-day termination notice was not given and “the deci
-
sion to terminate was made in an unprofessional manner
. . . conceived in frustration and consummated in anger.”
21
The lesson, to be safe, is that when terminating a contract,
do so pleasantly and with a smile on your face.
Finally, several additional issues exist with respect to
standard clauses in the American Institute of Architects
(“AIA”), Engineers Joint Contract Documents Commit-
tee (“EJCDC”), and ConsensusDocs® forms of “General
Conditions” relating to an owner’s right to terminate for
default by the contractor.
22
No authority has been found
determining whether the contractually-specied grounds
for termination supersede what might be a broader set
of situations comprising a substantial breach triggering
a common law termination option. In addition, while it
seems logical to conclude that the contractual scheme is
intended to be exclusive, as specically provided in the
ConsensusDocs®,
23
the existence of cumulative rem-
edy provisions in the other two standard forms strongly
indicate the contrary.
24
One might ask: What difference
does it make? The answer is that both of these contrac-
tual schemes require notice to be effective.
25
If an owner
improperly terminates without such a notice, a fallback
to the common law ground for the termination might be
very advantageous. As yet, there is no case law on the
effectiveness of such an approach.
Classification of Warranties and Related Breaches
Applying the three tiers of breach (substantial, material,
and immaterial/technical) to warranties is difcult due
to the nature of a given warranty or, more accurately, its
particular structure. One cannot accurately determine
the type of breach without rst determining what a war-
ranty really is. Despite the common usage of warranties,
the nature of a warranty is not often discussed insofar
as the time at which a warranty takes effect, aside from
specic contractual triggers.
26
For example, with a simple
“warranty against defects in material or workmanship, it
is unclear if the warranty is co-extensive with the basic
contractual obligation to perform in accordance with
contract requirements, or if it is a separate undertak-
ing.
27
There are obviously situations where warranties
are given as an independent contractual obligation, in
which event the warranty will usually commence upon
issuance. Because a warranty breach will occur if and
when the obligor fails to perform its warranty obliga-
tion and, in virtually all conceivable instances, when the
obligee has already been given full consideration for the
undertaking, there would not appear to be a situation
where a breach by the obligor could be considered sub-
stantial so as to trigger a First to Breach option for the
recipient. It is even less clear what happens when a war-
ranty is given as an integral part of the overall contractual
undertaking without separate consideration—what we
call an integrated warranty.
Even though an integrated warranty might be an essen-
tial component of a contract necessary for formation
purposes, unless its operability commences upon exe-
cution of the contract, it is difcult to imagine how its
breach could be considered a substantial one. Presum-
ably, the obligation to perform work free from defects
in material and workmanship is co-extensive with the
warranty undertaking until substantial completion is
achieved. The integrated warranty seems to offer little,
if anything, of value to this point, but with one possible
exception. For purposes of determining the existence of
a substantial breach of the base contract, thereby trigger-
ing a termination option, the focus is on the importance
of the obligation insofar as the essence of the transac-
tion is concerned. It would seem that there could not be
a breach of the companion warranty obligation indepen-
dent of the nature or signicance of the base contract
obligation being unfullled.
If a critical obligation is breached, it does little to
say the companion warranty obligation is also breached
unless one asserts that, within the four corners of the
warranty, there is a substantial breach independent of
the underlying contract breach. If this were the case, a
material breach of the base contract could be considered
a substantial breach of the warranty—–which seems to
make little sense. Consequently, it seems safe to conclude
that an integrated warranty will not confer any additional
rights worth considering by a obligee prior to substan-
tial performance of the base contract. It is presumed that
the warranty, although not so stated on its face, actu-
ally speaks as of the date of substantial performance. If
that is true, then a subsequent breach of the integrated
warranty cannot be considered a substantial breach trig-
gering a termination option for an owner even though it
was an essential term of the contract.
28
The owner might
exercise such option, for example, to avoid any remaining
payment obligations, although common law offset rights
would probably have the same effect.
The primary importance of the onset of a breach of an
THE CONSTRUCTION LAWYER8 Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
integrated warranty is the fact that such date will establish
the commencement of limitation periods for instituting
formal legal action.
29
To make such a determination, the
specic terms of the warranty must be carefully analyzed
because they will control the overall nal decision. Vari-
ants from a basic “warranty against defects in material
or workmanship” are several, including the presence or
absence of provisions related to a time period after which
the warranty is extinguished and (i) defects arising dur-
ing the warranty period without a requirement for notice
to activate a cure obligation or (ii) defects arising during
the warranty period wherein the warrantor receives writ-
ten notice of the claim within the specied time period.
Additional common features can include (i) the absence
of a specically stated obligation that the warrantor must
repair or replace the defect, (ii) a provision giving the
warrantor an option to correct the deciency prior to
the recipient acting on its own if the recipient wants to
hold the warrantor responsible, and (iii) a provision that
species whether or not the warranty is the recipient’s
sole remedy in the event of defects. If notice is required
to trigger a warranty performance obligation, a breach
could not occur nor a limitation period start running
until a reasonable time following such notice without an
appropriate cure.
When Is Warranty Performance Due?
If a party wrongfully terminates, or is properly termi-
nated, prior to substantial performance in a non-sales
transaction, both its base contract obligation as well as
its warranty obligations should survive that event. So far,
no conclusive authority has been found on this point, nor
does the case law focus on the character of the breach of
one’s warranty obligation.
30
Prior to substantial comple-
tion of the base contract, both the integrated warranty
and underlying performance obligation are essentially the
same. Courts generally look to the date that the instal-
lation or other performance is substantially completed
before any limitation period for ling claims commences.
This, obviously, has a distinct advantage in terms of sim-
plicity rather than addressing potential complexities
present with the actual warranty obligation. Rarely are
warranties crafted with specic terms addressing time for
performance and completion of the warranty obligation.
One impact of the date of a warranty breach is com-
mencement of the statute of limitations for contract
claims (including warranty claims). In other words, if
there is a six-year statute of limitations for breach of
contract claims, it may make a signicant difference if
the warranty is deemed breached upon substantial com-
pletion, due to defects in materials or workmanship, for
example, or at some later date. If a warranty provides the
obligor an opportunity to cure defects of which it receives
notice within a one-year warranty period, there are sev-
eral issues that should be addressed. For example, if the
obligor receives notice on the last day of the warranty
notice period, it obviously must have the right to per-
form its warranty obligation following the expiration of
that period.
31
Another issue is whether the warranty is
breached if the obligor fails to cure the defect on its rst
attempt, or whether it is entitled to multiple attempts and
over what period of time.
At this point, there is little if any authority on the issue
of whether it is “one strike and you’re out, apart from
the context of commencement of the statute of limita-
tions for breach of a cure warranty. A few cases discussing
the statute of limitations applicable to warranty breach
claims have concluded that when there are multiple unsuc-
cessful attempts to cure, the limitations period does not
start until the obligor “refuse[s] to make repairs.”
32
Sev-
eral cases have recognized that there are multiple ways in
which a cure warranty can be breached: (a) repudiating
the obligation before or after a demand to cure is made or
notice of defect is given; (b) failing to undertake repairs
within a reasonable time after the requirement is triggered;
(c) expressly refusing to repair; or (d) after undertaking a
repair, abandoning the effort prior to completion.
33
One
court has gone so far as to state that a refusal to repair
defective work under the base contract will result in a
separate contractual breach for which its own limitations
period and remedies will apply.
34
A similar series of issues arise with an open-ended
warranty covering defects that “arise or exist within” a
given warranty period regardless of when the condition
rst becomes apparent.
35
This type of warranty is per-
petual in that a construction defect will exist on the day
of substantial completion regardless of when it becomes
apparent. Without a requirement for notice of the con-
dition within a specied time period, the warranty will
continue to run forever, regardless of when the condition
rst becomes evident.
36
Regarding this particular type of
warranty, the same questions exist as to the time for com-
mencement and completion of warranty performance.
Must cure efforts be started within a certain period of
time following notice of the claim, or can an obligor wait
until near the end of the warranty period before under-
taking the cure?
37
Presumably, the implied obligation of
good faith would require commencement of cure efforts
within a reasonable time following notice.
38
An issue also
arises with respect to a warranty obligor’s liability for any
direct or consequential damages that are sustained fol-
lowing notice and prior to a nal effective cure.
39
Another issue, as referenced above, involves the ques-
tion of whether a warranty obligor is entitled to make
multiple attempts to cure the problem before a breach
actually occurs—and, if so, how many and over what
period of time.
40
While a warranty recipient’s obligation
to mitigate its damages may require allowing the obli-
gor subsequent cure efforts, there is unlikely to be any
provision in the warranty itself addressing this question.
Absent specic contractual language in the warranty, the
question of mitigation is not one of breach of a recipient’s
THE CONSTRUCTION LAWYER 9Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
warranty obligation to allow multiple cure efforts but
rather one of limiting or precluding the recipient’s dam-
ages recovery.
Also, warranties frequently do not specify a right for
the obligor to attempt a cure of the defect, although it
seems implicit and is explicit in major standard-form con-
tracts.
41
Absent such a clear right, a recipient should be
entitled to engage a third party to cure the deciency and
seek recovery of the related expenses.
42
Doing so, however,
could jeopardize the recipient’s right to recover a portion
or all of any other direct damages arising from the defect,
in addition to inviting a failure to mitigate defense by the
warranty obligor.
A related issue is whether the base contract’s warranty
against defects arising within, for example, one year also
creates a new one-year warranty regarding defects in the
purported cure that is performed. Only one set of the
major standard-form contracts specically provides for
a one-year warranty on warranty work.
43
Absent such a
clear contractual solution to the issue of defectively per-
formed warranty work, it seems clear that any purported
warranty “x” that is later discovered to be an ineffective
cure should result in a breach of the obligor’s warranty
obligation whenever discovered during the period of the
relevant statute of limitations.
44
Otherwise, a purported
cure implemented on the last day of the warranty period
might fail on the next day without the recipient having
any further recourse if the integrated warranty was des-
ignated the exclusive remedy. In support of this position
is the general rule that ambiguities are construed most
strictly against the drafter. Because the obligor invari-
ably drafts the warranty provision, it should bear the risk
associated with such extended coverage for the recipient.
This is not to say persuasive arguments might be crafted
to the contrary, although there does not appear to be
any denitive guidance in this respect. Finally, thought
should be given to whether the structural operation of
the warranty can amount to a frustration of purpose so
as to invalidate the problematic features.
45
Other issues arise with respect to a recipient’s right to
partially correct a defect as a part of its mitigation obliga-
tion while awaiting warranty performance by the obligor
without jeopardizing its right to recoup expenditures in
that effort. If the warranty is structured as an exclusive
remedy for the recipient, this becomes particularly trou-
blesome. A savvy practitioner will recognize this potential
problem and craft language to mitigate or eliminate such
an effect. Likewise, an owner should accept an exclusive
integrated warranty with a limitation on its term only if it
excludes claims for latent defects rst appearing after the
exclusivity period expires so that recourse can be available
under the base contract for the full period of the appli
-
cable statute of limitations or repose.
The Designer’s Implied Warranty
As any seasoned practitioner knows, an owner impliedly
warrants the adequacy of a design specication furnished
by its designer.
46
The obvious problem for the owner is
that by virtue of a deciency in the design documents,
it may be faced with a contractor’s claim for extra com-
pensation. Yet, if the owner cannot recoup that liability
from its designer, it will be left with an unexpected bill to
pay without having budgeted the expense. To successfully
pass through that liability to its designer, the owner will
look to enforce the implied warranty that it receives from
the designer. But what is the nature of that implied war-
ranty? One case describes in some detail the underlying
rationale for denying an implied warranty of “a satis-
factory result” amounting to strict liability for designers
absent the failure to satisfy the negligence standard of
care.
47
This is so regardless of whether a claim is pursued
on the basis of contract or tort obligations.
48
An attempt
to close the gap, so to speak, by imposing via contract a
standard of care higher than what an ordinary prudent
designer would have exercised under the same or similar
circumstances
49
creates a signicant problem for both the
designer and the owner. Namely, the designer’s errors and
omissions insurance coverage would, in all likelihood, be
inapplicable, leaving the designer “naked” from a cover-
age point of view.
The scope of a warranty creates problems as well.
While the usual warranty covers workmanship and mate-
rials, this overlooks the issue of design. For example,
the builder of a spec home provided an extensive set of
warranties regarding the structure and equipment com-
ponents; the home happened to be built in the midst of
an underground stream, necessitating installation of a
sump pump system. Unfortunately for the new owner, the
system was grossly undersized such that the sump pump
ran 24 hours a day, seven days a week, and burned out
in short order. In addition, the sump pit was too small
to handle the inux of water. The builder asserted that it
was not responsible for the condition, insisting that there
was no express or implied warranty as to the adequacy of
the system’s design and that the components of the sys-
tem were neither defective in workmanship or materials.
Ultimately, in that case, the builder recognized that the
law would in all likelihood imply a warranty of adequate
design, thereby prompting a settlement of the dispute.
50
Subcontractor Warranty Issues
Little, if anything, has been written or judicially pro-
mulgated when it comes to the issues surrounding a
subcontractor’s integrated warranty that its work will
be free from defects in materials or workmanship.
51
The
most basic inquiry has to do with the question of when
a subcontractor’s warranty performance obligation com
-
mences. Is it with the substantial completion of its work,
or of the entire project (the latter being the traditional
trigger for the general contractor’s obligation)? If it is
deemed to commence upon completion of the subcon-
tractor’s work, then when does it expire? While the specic
THE CONSTRUCTION LAWYER10 Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
terms of that warranty are important for making such
determinations, in all likelihood, contractual specicity
on these issues will be lacking. That, however, may be
of little practical signicance because if a subcontractor
fails to perform its work free from such deciencies, the
prime contractor may simply assert a claim of breach
under the base subcontract.
One obvious additional issue revolves around whether
a prime contractor can have a First to Breach option
insofar as its subcontractors are concerned.
52
There is
no reason that a prime contractor should not have that
remedy in the event of a substantial breach by the sub-
contractor. In such event, the prime contractor could use
the breach as a means of discharging the subcontractor
from the job, while also potentially relieving the prime
contractor from further obligations on its part and hold-
ing the subcontractor to the warranty obligations under
the subcontract. Of course, the question of substantial
breach of a subcontract can only occur if there is not sub-
stantial completion of that subcontract, regardless of the
stage of completion of the project as a whole. There does
not seem to be any basis for applying a different scheme
of breach labels to subcontracts than one would use with
respect to the prime contract.
Prime contractors who employ blanket “ow down”
clauses in their subcontracts create potential hidden prob-
lems for their subcontractors. The operative effect of a
“ow down” is to pass down to the subcontractor all obli-
gations relating to the subcontracted work that the prime
contractor has to the owner under the prime contract.
53
Absent some limiting language, this would include all
integrated warranty obligations. No court decision has
addressed the extent of a subcontractor’s warranty obli-
gation in such an event. Nevertheless, should the prime
contractors warranty be open-ended, running perpetu-
ally, then so too would the subcontractor’s warranty with
respect to its work. An experienced construction practi-
tioner reviewing a subcontract for her client will carefully
examine not only the scope of the “ow down” clause,
but also the particular structure of the prime contrac-
tor’s own warranty obligation in order to determine if
appropriate revisions are required to the subcontract so
as to avoid this exposure. The issues surrounding an open-
ended warranty obligation should therefore be worthy of
considerable attention.
Conclusion
People normally have little time to immerse themselves in
the implications of inconsistent and decient terminology
in the eld of jurisprudence. Nevertheless, an understand-
ing of the existing inconsistencies and deciencies in the
nomenclature surrounding contractual breach is a worth-
while undertaking in view of its signicant impact on the
proper creation, or assessment, of a party’s rights and lia-
bilities. The law of contractual breach in the construction
eld offers a solution to the deciencies inherent in the
traditional approaches. Lawyers knowledgeable in this
eld should be mindful of not only the issues surround-
ing the subject of breach, but also the need to export the
underlying terminology to areas beyond construction so
that eventually the courts will “get it right” and thereby
provide a commonsense basis for juries to arrive at fac-
tual determinations, while avoiding the risk of misleading
practitioners.
Jerey P. Aiken, Esq., jereypaiken@gmail.com, is an adjunct
professor of construction law at the University of Wisconsin Law
School and School of Engineering. Dylan C. Ochoa, Esq., dochoa@
hansonbridgett.com, is a construction associate practicing in Hanson
Bridgett LLP’s Los Angeles oce and an alum of the University
of Wisconsin Law School. For further information and questions
in connection with the article, please contact the authors at
jereypaik[email protected]om or dochoa@hansonbridgett.com
Endnotes
1. It is interesting to note that Black’s Law Dictionary, in dis-
cussing substantial performance, draws a distinction between
material and substantial without explanation of the difference.
Substantial Performance, B
lack
s
l
aw
D
ictionary
1281 (5th
ed. 1979) (“. . . the contract has been honestly and faithfully
performed in its material and substantial particulars”).
2. See, e.g., U.S. for the Use & Benet of Aucoin Elec. Sup-
ply Co. v. Safeco Ins. Co. of Am., 555 F.2d 535 (5th Cir. 1977);
Ditmar v. Beckham, 86 S.W.2d 801, 802 (Tex. Civ. App. 1935);
5 c
orBin
on
c
ontracts
§1110 (1964); Ehlinger v. Bodi Lake
Lumber Co., 36 N.W.2d 311, 316 (Mich. 1949) (“[H]e who com-
mits the rst substantial breach of a contract cannot maintain
an action against the other contracting party for failure to
perform.”).
3. See J.M. Beeson Co. v Sartori, 553 So. 2d 180, 182
(Fla. Dist. Ct. App. 1989); Reliance Ins. Co. v. Utah Dep’t of
Transp., 858 P.2d 1363, 1370 (1993, abrogated on other grounds
by Com. Real Est. Inv., L.C. v. Comcast of Utah II, Inc., 285
P.3d 1193, 1203 (Utah 2012); c.f. All Seasons Constr., Inc. v.
Manseld Hous. Auth., 920 So. 2d 413, 416 (La. 2006) (stating
that substantial completion was “referred to also as substantial
performance” and “can result even though deciencies exist”).
4. See Providence Wash. Ins. Co. v. Beck, 255 N.E.2d 600
(Mass. 1970) (holding failure to comply with a seven-day notice
of termination was “a substantial breach”).
5. Reid v. Mut. of Omaha Ins. Co., 776 P.2d 896, 906 (1989).
Mitigation is generally required when damages are sought in
tort cases, as well as in contract cases. See, e.g., Angelos v. First
Interstate Bank of Utah, 671 P.2d 772, 777 (1983); Jankele v.
Tex. Co., 54 P.2d 425, 428 (Utah 1936); restatement (seconD)
of torts § 918(1) (am. l. inst. 1979).
6. See a
m
. i
nst
.
of
a
rchitects
, aia 201-2017, G
eneral
conDitions of the contract for construction § 14.2 (2017)
[hereinafter AIA Documents].
7. See Nowicki-Hockey v. Bank of Am., 2017 Mich. App.
LEXIS 1069 (2017) (applying substantial breach in the context
of a loan transaction); Oak St. Funding, LLC v. Ingram, 749
THE CONSTRUCTION LAWYER 11Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
F. Supp. 2d 568, 574 (2010) (“[H]e who commits the rst sub-
stantial breach of a[n] [employment] contract cannot maintain
an action against the other contracting party for failure to per-
form.” (quoting Chrysler Int’l Corp. v. Cherokee Exp. Co., 134
F.3d 738, 742 (6th Cir. 1998) (quoting Ehlinger, 36 N.W.2d 311)).
8. Flaig v. Gramm, 1999 MT 181, ¶ 25 (1995) (“A substan-
tial or material breach is one which touches the fundamental
purposes of the contract and defeats the object of the parties
in making the contract.”); see also Gas Sensing Tech. Corp. v.
New Horizon Ventures Pty Ltd, 2020 WY 114 (2020) (nding
“material” breach and “substantial” breach to be synonymous for
purposes of justifying termination by the nonbreaching party).
9. See, e.g., Eagle Ridge L.L.C. v. Albert Homes, L.L.C.,
2009 WL 3837413 (Mich. Ct. App. 2009) (rst to breach must
be “substantial” to justify application of the First to Breach
defense); Flaig, 1999 MT 181, ¶ 25 (“A substantial or material
breach is one which touches the fundamental purposes of the
contract and defeats the object of the parties in making the
contract.”).
10. This disregards the potential impact of aesthetics as a
critical or nonessential component of the transaction. While
color may have signicance to its function, in many cases it is
purely a question of aesthetics. The signicance of aesthetic
considerations involves consideration of the subjective value of
the aesthetic component. In those jurisdictions where the courts
have focused on subjective value, cost of repair has been the
measure of damages regardless of diminished value. See Gory
Associated Indus. v. Jupiter Roong, 358 So. 2d 93 (Fla. Dist. Ct.
App. 1978); Lyon v. Belosky Constr. Inc., 247 A.D.2d 730, 669
N.Y.S.2d 400 (N.Y. App. Div. 3d 1998); Advanced Inc. v Wilks,
711 P.2d 524 (Alaska 1985); Fox v. Webb, 268 Ala. 111 (1958).
11. See U.S. for Use of Morgan & Son Earth Moving, Inc. v.
Timberland Paving & Constr. Co., 745 F.2d 595, 599–600 (9th
Cir. 1984); c.f. Olwell v. Nye & Nissen Co., 173 P.2d 652, 654
(Wash. 1946). An exception applies in the construction eld as
a result of the almost unavoidable use of changes to the original
contract terms. Basic contract liability for consequential dam-
ages is limited to the extent that such damages were foreseeable
at the time the contract was entered into. So far, no authority
has been found to resolve the question of whether entry of a
change order moves the foreseeability determination date for-
ward from the original contract entry date. However, in a recent
case, the U.S. District Court for the Middle District of Penn-
sylvania apparently ignored change order requests submitted
by a contractor when construing the foreseeability of ofce
overhead damages incurred on a library construction project.
Scartelli Constr. Servs., Inc. v. Chesapeake Bldg. Components,
Inc., No. 3:18-CV-01164, WL 3493145, slip op. at *5 (M.D.
Pa. 2021) (“[H]ere, Scartelli has provided evidence . . . that the
other change order requests on the project were related to the
truss system delay . . . but it has not provided any evidence to
show that ofce overhead damages were a foreseeable result
of that delay.”).
12. See, e.g., Durr Mech. Constr., Inc. v. PSEG Fossil, LLC,
516 F.Supp. 3d 407, 414 (D.N.J. 2021) (stating that a cardinal
change occurs when there is a such a drastic change in the work
that it effectively “requires the contractor to perform duties
materially different from those bargained for” (quoting Rums-
feld v. Freedom NY, Inc., 329 F.3d 1320, 1332 (Fed. Cir. 2003));
Krygoski Constr. Co., Inc. v. United States, 94 F.3d 1537, 1537
(Fed. Cir. 1996) (holding extent of changes sufciently extensive
where contract price effectively doubled); c.f. Baistar Mech., Inc.
v. United States, 128 Fed. Cl. 504, 504 (2016) (stating cardinal
change results in a breach of contract).
13. Becho, Inc. v. United States, 47 Fed. Cl. 595, 595 (2000)
(nding cardinal change and allowing contractor option to
either terminate or continue performance and receive compen-
sation for extra work on a time and materials basis); Big Chief
Drilling Co. v. United States, 26 Ct. Cl. 1276, 1276 (1992) (nd-
ing government insistence that contractor perform work with a
defective design specication constituted cardinal change and
supported contractor’s election for damages).
14. See, e.g., Allied Materials & Equip. Co., Inc. v. U.S., 215
Ct. Cl. 406, 410 (1978) (rejecting argument that changes clause
limited the scope of damages recoverable where cardinal change
doctrine applied).
15. Becho, Inc., 47 Fed. Cl. at 595 (holding damages to rea-
sonable services rendered under a time and materials scheme);
Big Chief Drilling Co., 26 Ct. Cl. at 1276 (1992) (holding dam-
ages to the reasonable value of changed work performed).
16. See Amelco Elec. v. City of Thousand Oaks, 27 Cal. 4th
228, 228 (2002). However, it appears that while not specically
recognizing changes by the term cardinal, the concept of aban-
donment has been used to address changes mid-project while
granting quantum meruit relief for the entire project. See Olbert
v. Ede, 38 Wis. 2d 240, 243 (1958).
17. See, e.g, Yonan v. Oak Park Fed. Sav. & Loan Ass’n, 27
Ill. App. 3d 967, 972 (stating universal rule that in construc-
tion contracts specic performance will not be enforced as (1)
there are adequate damages remedies at law and (2) courts lack
capacity to act as superintendents on construction projects); 71
am. Jur. 2D Contracts §90 (“[A]s a general rule, contracts for
building construction will not be specically enforced. . . .”).
18. However, courts generally require that the land trans-
fer be described with specicity in the parties’ agreement. See
Boardwalk at Daytona Dev., LLC, v. Paspalakis, 220 So. 3d
457, 459 (Fla. 2016).
19. Punitive damages are generally not permitted absent at
least some monetary damages award, albeit a slight one. E.g.,
State Farm Mut. Auto. Ins. Co. v. Campbell, 538 U.S. 408, 426
(2003).
20. See Patton v. Mid-Continent Sys., Inc., 841 F.2d 742,
751 (7th Cir. 1988) (“[E]ven if the breach is deliberate, it is not
necessarily blameworthy. The promisor may simply have discov-
ered that his performance is worth more to someone else. If so,
efciency is promoted by allowing him to break his promise, pro-
vided he makes good the promisee’s actual losses. If he is forced
to pay more than that, an efcient breach may be deterred, and
the law doesn’t want to bring about such a result.”).
21. Cuddy Mountain Concrete, Inc. v. Citadel Constr., Inc.,
824 P.2d 151 (Idaho 1992) (stating that post-termination revi-
sion of daily work records was “another factor which may
indicate that Cuddy Mountain is entitled to punitive damages,”
but without any explanation as to a jurisprudential basis for so
THE CONSTRUCTION LAWYER12 Volume 42 Issue 4
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
concluding).
22. aia Documents, supra note 6, § 14.2; enGrs Joint con-
tract Documents comm., eJcDc c-700, stanDarD General
conDitions of the construction contract § 16.02 (2018)
[hereinafter
eJcDc Documents]; consensusDocs®, stan-
DarD
a
Greement
anD
G
eneral
c
onDitions
B
etween
o
wner
anD contractor § 11.2 (2014).
23. ConsensusDocs® section 13.8 seems to explicitly provide
for noncumulative remedies by specifying that rights under the
agreement are exclusive.
consensusDocs®, supra note 22.
24. aia Documents, supra note 6, § 13.3.1; eJcDc Docu-
ments, supra note 22, § 18.03(A).
25. aia Documents, supra note 6, § 14.2.2; eJcDc Docu-
ments, supra note 22, § 16.02(B).
26. AIA Documents section 9.8.4 provides that general
warranties commence upon substantial completion. aia Doc-
uments
, supra note 6. EJCDC Documents section 15.08(A) is
of like effect. eJcDc D
ocuments
, supra note 22. In contrast,
ConsensusDocs® section 3.8.1 provides commencement upon
the date of nal payment or the date of certicate of substan-
tial completion. consensusDocs®, supra note 22.
27. Compare Hartford Accident & Indem. Co. v. Scarlett Har-
bor Assocs. Ltd. P’ship, 647 A.2d 106, 120 (Md. 1996) (treating
developer’s breach of contract and warranty claims as separate),
with D.R. Horton, Inc.–Denver v. Bischif & Coffman Constr.,
LLC, 217 P.3d 1262, 1272–74 (Colo. 2009) (holding that a breach
of warranty claim, while of necessity involving a contractual
breach, is separate from a breach of base contract obligations
and may result in different damages calculations).
28. So far, there is no authority on whether the effective
commencement date of an integrated warranty will move the
foreseeability determination date from original contract execu-
tion to potentially allow for recovery of consequential damages.
In fact, nothing has been found addressing the recoverability
of consequential damages in the event of a warranty breach,
although this might be expected to arise more with an indepen-
dent warranty.
29. Oftentimes, statutes of limitation are subject to exten-
sion by virtue of a discovery rule. Statues of repose, on the
other hand, are designed to provide an absolute claim cutoff,
not subject to discovery rule extension. Police & Fire Ret. Sys.
of City of Detroit v. IndyMac MBS, Inc., 721 F.3d 95, 106 (2d
Cir. 2013) (“[I[n contrast to statutes of limitations, statutes of
repose ‘create[] a substantive right in those protected to be free
from liability after a legislatively determined period of time.’”
(quoting Amoco Prod. Co. v. Newton Sheep Co., 85 F.3d 1464,
1472 (10th Cir. 1996) (emphasis and square brackets added by
IndyMac court))).
30. Hoagland v. Celebrity Homes, Inc., 572 P.2d 493, 494
(providing the measure of damages for breach of an implied
warranty of workmanship with respect to a construction con
-
tract without discussing the character of the breach).
31. See Antigua Condo. Ass’n v. Melba Invs. Atl., Inc., 517
A.2d 75, 82–84 (Md. 1986) (holding contractor was not required
to repair construction deciencies “instantly” upon its notice to
cure, but rather that there was a period of time during which
it could “investigate the problem and prepare to perform the
actual repair work” before the statute of limitations commenced).
32. Spinoso v. Rio Rancho Ests., Inc., 626 P.2d 1307, 1311
(N.M. Ct. App. 1981) (“During the three years following the
rst written notication of defects . . . , [the seller] made various
attempts at repair[,]” which were unsuccessful. Finally, the seller
refused to make further repairs and the purchaser sued.); Rob-
erts v. NVR, Inc., 2015 WL 3745178, at *3–4 (Pa. 2015) (denying
the general contractor’s motion to dismiss a complaint when the
homeowner adequately pled its breach of warranty claim after
the homeowner provided the contractor with adequate notice
and the contractor failed to correct alleged defects).
33. See Presidents & Dirs. of Geo. Coll. v. Madden, 505 F.
Supp. 557, 557 (D. Md. 1980), affd in part & appeal dismissed
in part, 660 F.2d 91, 91 (4th Cir. 1981); Beaudry Motor Co. v.
New Pueblo Constructors, Inc., 626 P.2d 1113, 1113 (Ariz. Ct.
App. 1981); Fowler v. A & A Co., 262 A.2d 344, 344 (D.C. 1970).
34. Geo. Coll., 505 F. Supp. at 557; see also Zellan v. Cole, 183
F.2d 139, 139 (D.C. Cir. 1950).
35. This would be the case if the provision merely species
it “warrants against defects in material and workmanship” or
“warrants against defects in material or workmanship arising
within (a specied period of time)” without a requirement that
would trigger the start of the warranty obligation upon notice
to the obligor within a specied time frame.
36. Structuring a warranty on an open-ended basis is a solu-
tion to the problem presented with an exclusive time-limited
warranty that would preclude relief for latent defects not dis-
coverable prior to the lapse of the warranty period.
37. Antigua Condo. Ass’n v. Melba Invs. Atl., Inc., 517 A.2d
75, 82–84 (Md. 1986).
38. Id. at 82; see also McClain v. Kimbrough Constr. Co., Inc.,
806 S.W.2d 194, 198 (Tenn. 1990) (stating general rule that parties
are expected to deal with each other fairly and in good faith even
where those principles are not embodied in the party’s contract).
39. Liability for consequential damages should be limited by
the foreseeability of those damages as of the time the warranty
was given as opposed to the time of any breach of that warranty.
C.f. Hadley v. Baxendale, 9 Exch. 345, 345 (1854) (holding that
consequential damages are limited to those foreseeable at the
time of contracting).
40. Antigua, 517 A.2d at 82; see also Magnum Constr. Mgmt.
Corp. v. City of Miami Beach, 209 So. 3d 51, 54–55 (Fla. Dist.
Ct. App. 3d Dist. 2016) (upholding a public contract provision
requiring the owner to provide a period of time within which a
period to cure must be performed by a contractor).
41. AIA Documents section 12.2.2.1 requires the owner to
Prime contractors who employ blanket
“flow down” clauses in their subcon-
tracts create potential hidden problems
for their contractors.
THE CONSTRUCTION LAWYER 13Volume 42 Issue 4
BUILDING A THRIVING ORGANIZATION —WHAT’S YOUR ROLE?
(Continued from page 4)
Published in
The Construction Lawyer
, Volume 42, Number 4. © 2023 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not
be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
give notice and a right to cure in order to avoid a waiver of its
warranty rights. aia D
ocuments
, supra note 6. So does Con-
sensusDocs® section 3.9.1 and EJCDC Documents section 3.9.1.
c
onsensus
D
ocs
®, supra note 22; eJcDc D
ocuments
, supra note
22. See ACE Sec. Corp. v. DB Structured Prods., Inc., 25 N.Y.3d
581, 589 (N.Y. 2015) (holding that the notice to cure as provided
by the parties’ contract was a substantive condition precedent to
ling suit and that plaintiffs failure to provide an opportunity
to cure was fatal to its breach of contract claim).
42. McClain, 806 S.W.2d 194 at 198 (holding that general
contractor may, after giving its subcontractor notice and a reason-
able opportunity to cure alleged defects, rescind the subcontract,
seek another subcontractor to perform the curative work, and
recover damages).
43. eJcDc Documents, supra note 22, § 15.08. AIA Doc-
uments section 12.2.2 has no comparable provision, nor does
ConsensusDocs® section 3.9.4. aia Documents, supra note
6; consensusDocs®, supra note 22. ConsensusDocs® provides
that if there is an unsatisfactory cure of defective work within the
correction period, the owner shall give the contractor an option
to further correct that work.
44. Roberts v. NVR, Inc., 2015 WL 3745178, at *3–4 (Pa.
2015) (denying general contractor’s motion to dismiss complaint
as homeowner adequately pled its breach of warranty claim after
the homeowner provided the contractor with sufcient notice and
the contractor failed to correct alleged defects).
45. For frustration of purpose as a separate theory, see Cutter
Labs, Inc. v. Twining, 221 Cal. App. 2d 302, 314–15 (1963) (stating
elements of a frustration of purpose claim); and Lloyd v. Murphy,
25 Cal. 2d 48, 48 (1944) (outlining public policy principles to con-
sider when construing equities in a frustration of purpose claim).
46. United States v. Spearin, 248 U.S. 132, 132 (1918).
47. City of Mounds View v. Walijarvi, 263 N.W.2d 420, 423
(Minn. 1978) (“Architects, . . . engineers, . . . and others deal in
somewhat inexact sciences and are continually called upon to
exercise their skilled judgment in order to anticipate and provide
for random factors which are incapable of precise measurement.
. . . Because of the inescapable possibility of error which inheres
in these services, the law has traditionally required, not perfect
results. . . . If every facet of structural design consisted of little
more than the mechanical application of immutable physical
principles, we could accept the rule of strict liability which the
city proposes. But even in the present state of relative techno-
logical enlightenment, the keenest engineering minds can err. . .
.Id. at 424.).
48. Balfour Beatty Infrastructure, Inc. v. Rummel Klepper &
Kahl, LLP, 130 A.3d 1024, 1034–35 (Md. 2017) (holding eco-
nomic loss doctrine precluded contractor’s negligence claim
against a designer for allegedly defective design work). The sig-
nicance of the legal theory lies in the respective statutes of
limitations in that negligence-based claims traditionally have
a considerably shorter period to le suit than contract claims.
49. Examples are requiring the designers abide by the highest
or most conservative design standards in the industry.
50. In this case, an equitable principle also came into play.
The colloquial version is “as between two innocent parties the
guilty one must suffer.” More precisely, as stated in Montgomery
Ward & Co. v. Peter J. McBreen & Associates, “the law abounds
in the proposition that as between two innocent parties, the less
blameful should prevail.” 40 Ill. App. 3d 69, 72 (1976); see also
Edwards v. Mid-Continent, 252 S.W.3d 833, 838 (Tex. Ct. App.
5th Dist. 2008) (“[C]ourts have held that as between two inno-
cent parties, the party that must suffer the loss is the one that
mistakenly created the situation and was in the best position to
have avoided it.”).
51. But see Lockheed Martin Transp. Sec. Sols. v. MTA
Capital Constr. Co., 2014 WL 12560868, at *28 (S.D.N.Y. 2014)
(denying contractor’s motion for summary judgment on its
breach of warranty claim against a subcontractor whose war-
ranty period had not yet been triggered). In Lockheed, the court
noted that MTA had failed to produce any case law to support
an anticipatory breach of warranty where the warranty period
had not yet been triggered. Id.
52. For example, in Scheck Industrial Corp. v. Tarlton Corp.,
the court, in a breach of warranty claim by a general contrac-
tor against its subcontractor, rejected the subcontractor’s First
to Breach defense that the general contractor’s failure to pro-
vide access to the contract documents relieved the subcontractor
from its warranty breach. Scheck, 435 S.W.3d 705, 727–28 (Mo.
Ct. App. 2014).
53. The subcontractor, under a “ow down, also acquires
all rights against the prime that the prime has against the owner
under the prime contract.
with expertise in a wide range of specialties. As with any
good community, we support our own--many of us will
only use consultants who actively support the Forum.
All of the attorney/consultant volunteers are guided
and supported by the steady hand of our incredible
ABA staff. The amount of work that goes “behind the
scenes” is astounding. Tamara Harrington, Patricia Har-
ris, Shannon Costis, and Colleen Hardison accomplish a
tremendous amount of work to make sure the volunteer
attorneys and consultants look organized and polished.
There are too many people to thank them individually,
but I am grateful to have such incredible support in my
role as Chair. As a parting thought, I would ask you to
think about the things you enjoy about the Forum and
spend a moment to contemplate all the work that went
into making that happen. Then I hope your next thought
turns to how you can get more involved to create those
special moments for future construction lawyers.